Project Duration
Stipulated Date of Commencement
June 16 2011
Stipulated Date of Completion /
Likely Date of Completion November 15 2011
Likely Date of Completion November 15 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,57,17,757.00
Awarded for
₹ 23,604,023.00
Contractors
M/s. Manguirish Air Conditioning Co.
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.