Project Duration
Stipulated Date of Completion /
Likely Date of Completion
Status

Completed
 
Gallery Image
Contractors
Gallery Image
Consultants
 

Sub Works

This project involved 20 sub works. The details of the same available below

1

Construction of District Headquarters Office Building Complex for South Goa District at Margao, Salcete, Goa -Civil, Plumbing, Internal Electrical & Fire Fighting works

100% completed
 
Project Duration
Stipulated Date of Commencement December 21 2007
Stipulated Date of Completion /
Likely Date of Completion
June 20 2010
Status
100%
Completed
Cost (₹)
Estimated at ₹ 573,453,985.00
Awarded for ₹ 734,634,449.00

Project highlights

Basement + Ground + 5 RCC framed structure

 
Contractors
Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd.
Consultants
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
2

Lift work

100% completed
 
Project Duration
Stipulated Date of Commencement February 16 2010
Stipulated Date of Completion /
Likely Date of Completion
August 15 2010
Status
100%
Completed
Cost (₹)
Estimated at ₹ 27,729,540.00
Awarded for ₹ 27,700,000.00
 
Contractors
Contractors
M/s. Thyssenkrupp Elevators (I) Pvt. Ltd.
Consultants
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
3

External Electrical works.

100% completed
 
Project Duration
Stipulated Date of Commencement February 16 2010
Stipulated Date of Completion /
Likely Date of Completion
August 15 2010
Status
100%
Completed
Cost (₹)
Estimated at ₹ 2,33,96,780.00
Awarded for ₹ 21,149,474.00
 
Contractors
Contractors
M/s. Imperial Engineering Co.
Consultants
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
4

Air conditioning works.

100% completed
 
Project Duration
Stipulated Date of Commencement June 16 2011
Stipulated Date of Completion /
Likely Date of Completion
November 15 2011
Status
100%
Completed
Cost (₹)
Estimated at ₹ 2,57,17,757.00
Awarded for ₹ 23,604,023.00
 
Contractors
Contractors
M/s. Manguirish Air Conditioning Co.
Consultants
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
5

Internal, external and special lighting fixtures (Part A – Supply of internal light fixtures / fans)

100% completed
 
Project Duration
Stipulated Date of Commencement September 15 2011
Stipulated Date of Completion /
Likely Date of Completion
January 14 2012
Status
100%
Completed
Cost (₹)
Estimated at ₹ 1,27,37,030.00
Awarded for ₹ 9,146,323.00
 
Contractors
Contractors
M/s. Eagle Construction Co.
Consultants
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
6

Audio Visual Equipments for conference system and AV room

100% completed
 
Project Duration
Stipulated Date of Commencement September 15 2011
Stipulated Date of Completion /
Likely Date of Completion
January 14 2012
Status
100%
Completed
Cost (₹)
Estimated at ₹ 2,34,15,719.00
Awarded for ₹ 13,448,394.00
 
Contractors
Contractors
M/s. Siemens Enterprises Communications Pvt. Ltd.
Consultants
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
7

Telephone Exchange and UPS (Part A- UPS work)

100% completed
 
Project Duration
Stipulated Date of Commencement September 15 2011
Stipulated Date of Completion /
Likely Date of Completion
January 14 2012
Status
100%
Completed
Cost (₹)
Estimated at ₹ 44,92,891.00
Awarded for ₹ 4,693,205.00
 
Contractors
Contractors
M/s. Imperial Engineering Co.
Consultants
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
8

Telephone Exchange and UPS (Part B – IP Telephony and Video Conferencing work)

100% completed
 
Project Duration
Stipulated Date of Commencement February 01 2012
Stipulated Date of Completion /
Likely Date of Completion
March 16 2012
Status
100%
Completed
Cost (₹)
Estimated at ₹ 1,00,26,362.00
Awarded for ₹ 5,637,190.00
 
Contractors
Contractors
M/s. Siemens Enterprises Communications Pvt. Ltd.
Consultants
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
9

Decorative Glazing for staircase blocks.

100% completed
 
Project Duration
Stipulated Date of Commencement April 22 2012
Stipulated Date of Completion /
Likely Date of Completion
May 07 2012
Status
100%
Completed
Cost (₹)
Estimated at ₹ 87,89,272.80
Awarded for ₹ 8,250,144.00

Project highlights

Decorative Glazing works

 
Contractors
Contractors
M/s. R. S. Lawande
Consultants
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
10

Carpentry and interior work.

100% completed
 
Project Duration
Stipulated Date of Commencement April 22 2012
Stipulated Date of Completion /
Likely Date of Completion
August 21 2012
Status
100%
Completed
Cost (₹)
Estimated at ₹ 4,96,84,461.30
Awarded for ₹ 53,022,057.00

Project highlights

Carpentry works

 
Contractors
Contractors
M/s.Concept Creator
Consultants
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
11

Readymade furniture works

100% completed
 
Project Duration
Stipulated Date of Commencement July 09 2012
Stipulated Date of Completion /
Likely Date of Completion
June 12 2012
Status
100%
Completed
Cost (₹)
Estimated at ₹ 4,28,94,732.00
Awarded for ₹ 37,798,417.00

Project highlights

Readymade Furniture works

 
Contractors
Contractors
M/s. Durian Industries Ltd.
Consultants
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
12

Internal, external and special lighting fixtures (Part B : External lights and façade lighting)

100% completed
 
Project Duration
Stipulated Date of Commencement August 11 2012
Stipulated Date of Completion /
Likely Date of Completion
December 23 2012
Status
100%
Completed
Cost (₹)
Estimated at ₹ 1,09,68,986.00
Awarded for ₹ 6,849,960.00
 
Contractors
Contractors
M/s. Shanti Electrical Enterprises Pvt. Ltd.
Consultants
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
13

Supply of trees, grass, grass covers & allied material for landscaping works.

100% completed
 
Project Duration
Stipulated Date of Commencement January 17 2013
Stipulated Date of Completion /
Likely Date of Completion
February 15 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 17,02,563.00
Awarded for ₹ 2,983,810.00

Project highlights

Landscaping works

 
Contractors
Contractors
M/s. Vrindavan Agricultural Services
Consultants
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
14

Signages work

100% completed
 
Project Duration
Stipulated Date of Commencement January 27 2013
Stipulated Date of Completion /
Likely Date of Completion
February 25 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 43,59,583.00
Awarded for ₹ 4,023,779.00

Project highlights

Signages works

 
Contractors
Contractors
M/s. Harshada Trading Co.
Consultants
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
15

Supply, installation, testing and commissioning of Precision AC, UPS, D. G. Set, Transformer, and related electrical works

100% completed
 
Project Duration
Stipulated Date of Commencement January 31 2013
Stipulated Date of Completion /
Likely Date of Completion
April 30 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 17,228,580.00
Awarded for ₹ 16,956,091.00
 
Contractors
Contractors
M/s. Ohm Engineers & Electricals Pvt. Ltd.
Consultants
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
16

CPOE switches

100% completed
 
Project Duration
Stipulated Date of Commencement April 12 2012
Stipulated Date of Completion /
Likely Date of Completion
October 01 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ ----
Awarded for ₹ 1,539,900.00
 
Contractors
Contractors
M/s. AGC Networks Limited
Consultants
Consultants
In-house (GSIDC)
17

Supply & Installation of Compactors in Record Room of Survey Department and Sub Civil Registrar.

100% completed
 
Project Duration
Stipulated Date of Commencement October 12 2013
Stipulated Date of Completion /
Likely Date of Completion
December 11 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 2,321,131.00
Awarded for ₹ 2,375,201.00

Project highlights

Compactors in Record rooms

 
Contractors
Contractors
M/s. Kompress (India) Pvt. Ltd.
Consultants
Consultants
In-house (GSIDC)
18

Raising the Existing Compound Wall and Providing Additional Gutters

100% completed
 
Project Duration
Stipulated Date of Commencement October 16 2013
Stipulated Date of Completion /
Likely Date of Completion
February 15 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 5,002,100.00
Awarded for ₹ 4,991,914.50

Project highlights

Additional gutters & Compound wall works

 
Contractors
Contractors
M/s. A. Ponnuraj
Consultants
Consultants
In-house (GSIDC)
19

– Additional Miscellaneous work.

100% completed
 
Project Duration
Stipulated Date of Commencement January 23 2015
Stipulated Date of Completion /
Likely Date of Completion
May 22 2015
Status
100%
Completed
Cost (₹)
Estimated at ₹ 14,853,393.00
Awarded for ₹ 13,328,661.00

Project highlights

Additional furniture & minor civil works.

 
Contractors
Contractors
M/s. Concept Creators
Consultants
Consultants
M/s. Nitin Arolkar
20

Supply, installation, testing & commissioning of C1287 RMU

100% completed
 
Project Duration
Stipulated Date of Commencement April 23 2018
Stipulated Date of Completion /
Likely Date of Completion
June 22 2018
Status
100%
Completed
Cost (₹)
Estimated at ₹ 2,690,000.00
Awarded for ₹ 2,645,220.00
 
Contractors
Contractors
M/s. Pristine Engineering Services
Consultants
Consultants
In-house (GSIDC)
Similar Projects

See Similar Projects

Similar Project

Renovation of Building of Directorate of Higher Education, Porvorim, Goa – Fire Fighting System work.

View Project
Similar Project

Painting, landscaping and other ancillary works along DB Road Panaji for IFFI 2017- SH: Resurfacing of Roads

View Project
Similar Project

Providing 11 KV transformer substation for release of electrical connection to the office premises of Commercial Tax Office, Ponda .

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.