Project Duration
Stipulated Date of Completion /
Likely Date of Completion
Likely Date of Completion
Status
Completed
Contractors
Consultants
Sub Works
This project involved 20 sub works. The details of the same available below
1
Construction of District Headquarters Office Building Complex for South Goa District at Margao, Salcete, Goa -Civil, Plumbing, Internal Electrical & Fire Fighting works
100% completed
Project Duration
Stipulated Date of Commencement
December 21 2007
Stipulated Date of Completion /
Likely Date of Completion June 20 2010
Likely Date of Completion June 20 2010
Status
100%
Completed
Cost (₹)
Estimated at
₹ 573,453,985.00
Awarded for
₹ 734,634,449.00
Project highlights
Basement + Ground + 5 RCC framed structure
Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd.
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
2
Lift work
100% completed
Project Duration
Stipulated Date of Commencement
February 16 2010
Stipulated Date of Completion /
Likely Date of Completion August 15 2010
Likely Date of Completion August 15 2010
Status
100%
Completed
Cost (₹)
Estimated at
₹ 27,729,540.00
Awarded for
₹ 27,700,000.00
Contractors
M/s. Thyssenkrupp Elevators (I) Pvt. Ltd.
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
3
External Electrical works.
100% completed
Project Duration
Stipulated Date of Commencement
February 16 2010
Stipulated Date of Completion /
Likely Date of Completion August 15 2010
Likely Date of Completion August 15 2010
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,33,96,780.00
Awarded for
₹ 21,149,474.00
Contractors
M/s. Imperial Engineering Co.
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
4
Air conditioning works.
100% completed
Project Duration
Stipulated Date of Commencement
June 16 2011
Stipulated Date of Completion /
Likely Date of Completion November 15 2011
Likely Date of Completion November 15 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,57,17,757.00
Awarded for
₹ 23,604,023.00
Contractors
M/s. Manguirish Air Conditioning Co.
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
5
Internal, external and special lighting fixtures (Part A – Supply of internal light fixtures / fans)
100% completed
Project Duration
Stipulated Date of Commencement
September 15 2011
Stipulated Date of Completion /
Likely Date of Completion January 14 2012
Likely Date of Completion January 14 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,27,37,030.00
Awarded for
₹ 9,146,323.00
Contractors
M/s. Eagle Construction Co.
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
6
Audio Visual Equipments for conference system and AV room
100% completed
Project Duration
Stipulated Date of Commencement
September 15 2011
Stipulated Date of Completion /
Likely Date of Completion January 14 2012
Likely Date of Completion January 14 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,34,15,719.00
Awarded for
₹ 13,448,394.00
Contractors
M/s. Siemens Enterprises Communications Pvt. Ltd.
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
7
Telephone Exchange and UPS (Part A- UPS work)
100% completed
Project Duration
Stipulated Date of Commencement
September 15 2011
Stipulated Date of Completion /
Likely Date of Completion January 14 2012
Likely Date of Completion January 14 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 44,92,891.00
Awarded for
₹ 4,693,205.00
Contractors
M/s. Imperial Engineering Co.
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
8
Telephone Exchange and UPS (Part B – IP Telephony and Video Conferencing work)
100% completed
Project Duration
Stipulated Date of Commencement
February 01 2012
Stipulated Date of Completion /
Likely Date of Completion March 16 2012
Likely Date of Completion March 16 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,00,26,362.00
Awarded for
₹ 5,637,190.00
Contractors
M/s. Siemens Enterprises Communications Pvt. Ltd.
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
9
Decorative Glazing for staircase blocks.
100% completed
Project Duration
Stipulated Date of Commencement
April 22 2012
Stipulated Date of Completion /
Likely Date of Completion May 07 2012
Likely Date of Completion May 07 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 87,89,272.80
Awarded for
₹ 8,250,144.00
Project highlights
Decorative Glazing works
Contractors
M/s. R. S. Lawande
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
10
Carpentry and interior work.
100% completed
Project Duration
Stipulated Date of Commencement
April 22 2012
Stipulated Date of Completion /
Likely Date of Completion August 21 2012
Likely Date of Completion August 21 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 4,96,84,461.30
Awarded for
₹ 53,022,057.00
Project highlights
Carpentry works
Contractors
M/s.Concept Creator
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
11
Readymade furniture works
100% completed
Project Duration
Stipulated Date of Commencement
July 09 2012
Stipulated Date of Completion /
Likely Date of Completion June 12 2012
Likely Date of Completion June 12 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 4,28,94,732.00
Awarded for
₹ 37,798,417.00
Project highlights
Readymade Furniture works
Contractors
M/s. Durian Industries Ltd.
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
12
Internal, external and special lighting fixtures (Part B : External lights and façade lighting)
100% completed
Project Duration
Stipulated Date of Commencement
August 11 2012
Stipulated Date of Completion /
Likely Date of Completion December 23 2012
Likely Date of Completion December 23 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,09,68,986.00
Awarded for
₹ 6,849,960.00
Contractors
M/s. Shanti Electrical Enterprises Pvt. Ltd.
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
13
Supply of trees, grass, grass covers & allied material for landscaping works.
100% completed
Project Duration
Stipulated Date of Commencement
January 17 2013
Stipulated Date of Completion /
Likely Date of Completion February 15 2013
Likely Date of Completion February 15 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 17,02,563.00
Awarded for
₹ 2,983,810.00
Project highlights
Landscaping works
Contractors
M/s. Vrindavan Agricultural Services
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
14
Signages work
100% completed
Project Duration
Stipulated Date of Commencement
January 27 2013
Stipulated Date of Completion /
Likely Date of Completion February 25 2013
Likely Date of Completion February 25 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 43,59,583.00
Awarded for
₹ 4,023,779.00
Project highlights
Signages works
Contractors
M/s. Harshada Trading Co.
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
15
Supply, installation, testing and commissioning of Precision AC, UPS, D. G. Set, Transformer, and related electrical works
100% completed
Project Duration
Stipulated Date of Commencement
January 31 2013
Stipulated Date of Completion /
Likely Date of Completion April 30 2013
Likely Date of Completion April 30 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 17,228,580.00
Awarded for
₹ 16,956,091.00
Contractors
M/s. Ohm Engineers & Electricals Pvt. Ltd.
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
16
CPOE switches
100% completed
Project Duration
Stipulated Date of Commencement
April 12 2012
Stipulated Date of Completion /
Likely Date of Completion October 01 2013
Likely Date of Completion October 01 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ ----
Awarded for
₹ 1,539,900.00
Contractors
M/s. AGC Networks Limited
Consultants
In-house (GSIDC)
17
Supply & Installation of Compactors in Record Room of Survey Department and Sub Civil Registrar.
100% completed
Project Duration
Stipulated Date of Commencement
October 12 2013
Stipulated Date of Completion /
Likely Date of Completion December 11 2013
Likely Date of Completion December 11 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,321,131.00
Awarded for
₹ 2,375,201.00
Project highlights
Compactors in Record rooms
Contractors
M/s. Kompress (India) Pvt. Ltd.
Consultants
In-house (GSIDC)
18
Raising the Existing Compound Wall and Providing Additional Gutters
100% completed
Project Duration
Stipulated Date of Commencement
October 16 2013
Stipulated Date of Completion /
Likely Date of Completion February 15 2014
Likely Date of Completion February 15 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 5,002,100.00
Awarded for
₹ 4,991,914.50
Project highlights
Additional gutters & Compound wall works
Contractors
M/s. A. Ponnuraj
Consultants
In-house (GSIDC)
19
– Additional Miscellaneous work.
100% completed
Project Duration
Stipulated Date of Commencement
January 23 2015
Stipulated Date of Completion /
Likely Date of Completion May 22 2015
Likely Date of Completion May 22 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 14,853,393.00
Awarded for
₹ 13,328,661.00
Project highlights
Additional furniture & minor civil works.
Contractors
M/s. Concept Creators
Consultants
M/s. Nitin Arolkar
20
Supply, installation, testing & commissioning of C1287 RMU
100% completed
Project Duration
Stipulated Date of Commencement
April 23 2018
Stipulated Date of Completion /
Likely Date of Completion June 22 2018
Likely Date of Completion June 22 2018
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,690,000.00
Awarded for
₹ 2,645,220.00
Contractors
M/s. Pristine Engineering Services
Consultants
In-house (GSIDC)
See Similar Projects
Renovation of Building of Directorate of Higher Education, Porvorim, Goa – Fire Fighting System work.
View Project
Painting, landscaping and other ancillary works along DB Road Panaji for IFFI 2017- SH: Resurfacing of Roads
View Project
Providing 11 KV transformer substation for release of electrical connection to the office premises of Commercial Tax Office, Ponda .
View Project