Project Duration
Stipulated Date of Commencement October 09 2012
Actual Date of Completion December 19 2012
Status
100%
Completed
Cost (₹)
Estimated at ₹ 2,923,512.21
Awarded for ₹ 3,083,239.00
 
Contractors
M/s. Vrindanvan Agricultural Services
Consultants
M/s. Intertek Architects & Consultants Pvt. Ltd.
 