Project Duration
Start Date 19/03/2007
End Date 15/06/2011
Status
100%
Completed
Cost (₹)
Estimated at ₹ 14,26,78,131.99
Awarded for ₹ 159,500,629.70
Final Cost of Project ₹ 504,761,049.00
 
Contractors
M/s. G. M. Bijlani Construction Pvt. Ltd.
Consultants
M/s. Architecture Autonomous / M/s. Frischmann Prabhu (I) Pvt. Ltd.
 

Additional Work

This project involved 27 additional tasks. The details of the same available below

Status Progress Project Duration
Start Date / End Date
Cost (Rs.)
Estimated / Awarded
Consultants & Contractors
1 Dehumidification System
100% completed
 
 

19/11/2010 - 04/01/2011

 

₹ - / ₹ 99,55,323.00

  M/s.Architecture Autonomous PMC with Frischmann Prabhu India (I) Pvt Ltd.
M/s. Bry Air (Asia) Pvt. Ltd. -
2 Dehumidification System.
100% completed
 
 

19/11/2010 - 14/08/2011

 

₹ - / ₹ 6,94,890.00

  M/s.Architecture Autonomous PMC with Frischmann Prabhu India (I) Pvt Ltd.
M/s. Technical Drying Services (Asia) Pvt. Ltd. -
3 Digital Multifunctional Copiers
100% completed
 
 

02/12/2010 - 31/08/2011

 

₹ 2,156,307.00 / ₹ 2,156,307.00

  Inhouse
M/s. Sharp Business Systems (India) Limited -
4 Fire Hydrant & Fire Alarm System.
100% completed
 
 

16/06/2009 - 30/11/2011

 

₹ 6,783,602.00 / ₹ 7,994,225.00

  M/s.Architecture Autonomous PMC with Frischmann Prabhu India (I) Pvt Ltd.
M/s. Hindustan Construction Corporation -
5 Glazing work.
100% completed
 
 

10/11/2010 - 15/09/2011

 

₹ 16,860,438.00 / ₹ 15,652,550.00

  M/s.Architecture Autonomous PMC with Frischmann Prabhu India (I) Pvt Ltd.
M/s. Simca Aluminium Pvt. Ltd. -
6 Modular Furniture works
100% completed
 
 

10/11/2010 - 28/09/2011

 

₹ 24,644,210.00 / ₹ 22,358,766.00

  M/s.Architecture Autonomous PMC with Frischmann Prabhu India (I) Pvt Ltd.
M/s. Space N Style -
7 Compound Wall & Site Development.
100% completed
 
 

15/02/2011 - 16/08/2011

 

₹ 17,150,885.00 / ₹ 17,177,265.00

  M/s.Architecture Autonomous PMC with Frischmann Prabhu India (I) Pvt Ltd.
M/s. A. Ponnuraj -
8 Signages.
100% completed
 
 

27/01/2011 - 25/08/2011

 

₹ 4,755,845.00 / ₹ 4,547,565.00

  M/s.Architecture Autonomous PMC with Frischmann Prabhu India (I) Pvt Ltd.
M/s. Harshada Trading Company -
9 Soft landscaping.
100% completed
 
 

15/02/2011 - 30/11/2011

 

₹ 1,567,620.00 / ₹ 1,882,585.00

  M/s.Architecture Autonomous PMC with Frischmann Prabhu India (I) Pvt Ltd.
M/s. Vrindavan Agricultural Services -
10 Seating works.
100% completed
 
 

30/04/2011 - 30/11/2011

 

₹ 8,655,070.00 / ₹ 6,793,290.00

  M/s.Architecture Autonomous PMC with Frischmann Prabhu India (I) Pvt Ltd.
M/s. Durian Industries Ltd. -
11 IP Surveillance System.
100% completed
 
 

06/12/2010 - 20/08/2011

 

₹ 8,571,330.00 / ₹ 8,292,525.00

  M/s.Architecture Autonomous PMC with Frischmann Prabhu India (I) Pvt Ltd.
M/s. Reconnoitre Systems -
12 Online UPS System.
100% completed
 
 

02/12/2010 - 25/08/2011

 

₹ 2,791,003.00 / ₹ 2,766,560.00

  M/s.Architecture Autonomous PMC with Frischmann Prabhu India (I) Pvt Ltd.
M/s. Accutech Power Solutions Pvt. Ltd. -
13 Air Conditioning work.
100% completed
 
 

23/04/2010 - 16/12/2011

 

₹ 33,031,108.00 / ₹ 31,600,001.95

  M/s.Architecture Autonomous PMC with Frischmann Prabhu India (I) Pvt Ltd.
M/s. Aparant Motors Pvt. Ltd. -
14 Electrical work.
100% completed
 
 

06/11/2008 - 20/10/2011

 

₹ 24,932,899.00 / ₹ 19,636,164.00

  M/s.Architecture Autonomous PMC with Frischmann Prabhu India (I) Pvt Ltd.
M/s. Imperial Engineering Company -
15 Carpentry work.
100% completed
 
 

15/11/2010 - 31/12/2011

 

₹ 23,148,451.00 / ₹ 18,422,874.33

  M/s.Architecture Autonomous PMC with Frischmann Prabhu India (I) Pvt Ltd.
M/s. Knchan Associates -
16 Desktop computers, printers & scanners.
100% completed
 
 

02/12/2010 - 15/09/2011

 

₹ 18,552,266.00 / ₹ 18,552,266.00

  Inhouse
M/s. Syscon Computers -
17 Digital Multifunctional Copiers
100% completed
 
 

02/12/2010 - 15/09/2011

 

₹ 2,940,292.00 / ₹ 2,940,292.00

  Inhouse
M/s. Richo Limited -
18 RFID System.
100% completed
 
 

10/01/2011 - 30/09/2011

 

₹ 13,491,547.00 / ₹ 13,491,547.00

  Inhouse
M/s. Libsys Ltd. -
19 Book Cutting Machine.
100% completed
 
 

13/01/2011 - 15/09/2011

 

₹ 1,680,000.00 / ₹ 1,680,000.00

  Inhouse
M/s. Mohansons India -
20 Zeutschel Book Scanner.
100% completed
 
 

22/12/2010 - 15/09/2011

 

₹ 2,677,500.00 / ₹ 2,677,500.00

  Inhouse
M/s. KGS Microsystems -
21 Additional light fixtures.
100% completed
 
 

19/09/2011 - 10/04/2012

 

₹ 6,575,575.00 / ₹ 4,886,125.00

  M/s.Architecture Autonomous
M/s. James Electrical -
22 Storm Water Drainage.
100% completed
 
 

23/04/2010 - 22/06/2010

 

₹ 1,900,530.00 / ₹ 1,988,414.00

  M/s.Architecture Autonomous PMC with Frischmann Prabhu India (I) Pvt Ltd.
M/s. Kamaxi Constructions -
23 Lifts.
100% completed
 
 

06/11/2008 - 09/06/2011

 

₹ 3,150,000.00 / ₹ 3,560,000.00

  M/s.Architecture Autonomous PMC with Frischmann Prabhu India (I) Pvt Ltd.
M/s. Thyssenkrup Electrical (I) Ltd. -
24 Dumb Waiter work.
100% completed
 
 

09/12/2010 - 09/06/2011

 

₹ 10,91,770.00 / ₹ 10,90,000.00

  M/s.Architecture Autonomous PMC with Frischmann Prabhu India (I) Pvt Ltd.
M/s. Thyssenkrupp Elevators (I) Pvt. Ltd. -
25 Additional electrical work.
100% completed
 
 

18/02/2010 - 25/08/2011

 

₹ 5,844,975.00 / ₹ 5,107,434.00

  M/s.Architecture Autonomous PMC with Frischmann Prabhu India (I) Pvt Ltd.
M/s. Imperial Engineering Company -
26 False ceiling work.
100% completed
 
 

28/02/2009 - 30/08/2011

 

₹ 12,988,688.00 / ₹ 12,968,300.00

  M/s.Architecture Autonomous PMC with Frischmann Prabhu India (I) Pvt Ltd.
M/s. Damian de Goa -
27 750 KVA Diesel Generator work
100% completed
 
 

04/12/2010 - 29/07/2011

 

₹ 74,60,421.00 / ₹ 72,37,840.00

  M/s.Architecture Autonomous PMC with Frischmann Prabhu India (I) Pvt Ltd.
M/s. Eagle Construction Co. -

See Similar Projects

Upgradation and Renovation of Market at Santemol, Raia (Tinto).

View Project

Construction of Community Hall in the Morlem Rehabilitation Colony in Sattari Taluka

View Project

Construction of Ravindra Bhavan at Baina, Vasco, Goa

View Project
x