Project Duration
Stipulated Date of Commencement
October 01 2017
Actual Date of Completion
November 30 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,999,277.00
Awarded for
₹ 1,963,600.00
Final Cost of Project
₹ 17/98/772.00
Contractors
M/S.Creation Interior Contractor
Consultants
M/s. Rahul Deshpande & Associates