Project Duration
Stipulated Date of Commencement
February 28 2015
Actual Date of Completion
October 10 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 13,233,916.00
Awarded for
₹ 13,253,000.00
Final Cost of Project
₹ 41,654,804.00
Project highlights
the entire area admeasuring 20081 sq.m was filled with moorum and compacted
Contractors
M/s. Sangam Construction
Consultants
M/s. Rahul Deshpande and Associates