Project Duration
Stipulated Date of Commencement February 17 2011
Stipulated Date of Completion /
Likely Date of Completion
July 16 2011
Status
100%
Completed
Cost (₹)
Estimated at ₹ 2,087,400.00
Awarded for ₹ 2,220,000.00
 
Gallery Image
Contractors
M/s. Eagle Construction Co.
Gallery Image
Consultants
Datta Kare Associates
 
Similar Projects

See Similar Projects

Similar Project

Maintenance Works of Goa Medical College and Hospital & Goa Dental College S.H.: Supply, Installation, Testing & Commissioning of 2 Nos. 5.5TR ductable units for MRI section at Goa Medical College, Bambolim-Goa.

View Project
Similar Project

Supply and Installation of Office Furniture

View Project
Similar Project

Internal Electrical works

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.