Project Duration
Stipulated Date of Commencement April 19 2012
Stipulated Date of Completion /
Likely Date of Completion
August 18 2012
Status
100%
Completed
Cost (₹)
Estimated at ₹ 35,214,351.00
Awarded for ₹ 18,028,622.54
 
Gallery Image
Contractors
M/s. Steel Case
Gallery Image
Consultants
M/s. Effective Architectural Services
 
Similar Projects

See Similar Projects

Similar Project

Ancillary civil works at Kala Academy and INOX, Panaji, Goa for IFFI 2012.

View Project
Similar Project

Supply & Installation of Compactors in Record Room of Survey Department and Sub Civil Registrar.

View Project
Similar Project

Igreja De Nossa Senhora de Ajuda Church Ribandar- Balance Civil, Electrical & Miscellaenous works

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.