Project Duration
Stipulated Date of Commencement
April 19 2012
Stipulated Date of Completion /
Likely Date of Completion August 18 2012
Likely Date of Completion August 18 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 35,214,351.00
Awarded for
₹ 18,028,622.54
Contractors
M/s. Steel Case
Consultants
M/s. Effective Architectural Services