Status
100%
Completed

Project highlights

Science Faculty Building is conceptualized to meet the ever-growing needs of expansion of the campus to incorporate study of Science, for quality research facility and to create an excellent, modern research facility.
The work is completed in all respects at a cost of Rs. 48.00 Crore approximately and inaugurated on 13th May 2013.
The building is basement plus 2 storied RCC framed structure.
The built-up area is 20210.00 Sqm.
The structure is planned with three blocks AB block, C block and DE block, Where C block is joining of two wings AB and DE having main entrance at the Ground floor and Library and offices on upper floors. AB Block and DE block comprises lecture hall, research lab and administration spaces.
The building comprises of two seminar halls. One in AB block having capacity of 180 No chairs and other in DE block having capacity of 325 No chairs.
There are four central open courtyards for natural light and ventilation into the rooms.
The building has six staircase blocks designed for public circulation and one internal staircase in the library. All the staircases are well equipped for fire escape. Also 4 Nos. of lifts are provided.
Building is well equipped with fire fighting equipments, networking facilities, lab furniture, fume hoods in labs, gas piping in labs, interior & acoustic, furniture, etc.
All the floors are provided with adequate toilet facilities, etc.
Parking facilities for four wheelers and two wheelers, RCC road, landscaping, STP & ETP, Gas Bank, Pump room etc.

 
 

Sub Works

This project involved 15 sub works. The details of the same available below

1

Construction of Building for Science Faculty at Goa University, Taleigao, Tiswadi Goa – Civil, electrification & land development work.

100% completed
 
Project Duration
Stipulated Date of Commencement March 27 2007
Stipulated Date of Completion /
Likely Date of Completion
Status
100%
Completed
Cost (₹)
Estimated at ₹ 203,081,980.00
Awarded for ₹ 228,194,428.97
Final Cost of Project ₹ 472,055,944.00
 
Contractors
M/s. D. S. Contractors Pvt. Ltd., M/s. D. S. Contractors Pvt. Ltd., M/s. D. S. Contractors Pvt. Ltd.
Consultants
M/s. Effective Architectural Services, M/s. Effective Architectural Services, M/s. Effective Architectural Services
2

Lifts / Elevator work.

100% completed
 
Project Duration
Stipulated Date of Commencement October 05 2009
Stipulated Date of Completion /
Likely Date of Completion
Status
100%
Completed
Cost (₹)
Estimated at ₹ 2,450,000.00
Awarded for ₹ 2,570,000.00
 
Contractors
M/s. Thyssenkrupp Elevator (India) Pvt. Ltd.
Consultants
M/s. Effective Architectural Services
3

Structural Steel, Roofing and Structural Glazing works

100% completed
 
Project Duration
Stipulated Date of Commencement August 14 2010
Stipulated Date of Completion /
Likely Date of Completion
April 30 2012
Status
100%
Completed
Cost (₹)
Estimated at ₹ 17,300,928.00
Awarded for ₹ 16,920,811.16
 
Contractors
M/s. D. S. Contractors Pvt. Ltd.
Consultants
M/s. Effective Architectural Services
4

External Electrical work

100% completed
 
Project Duration
Stipulated Date of Commencement November 27 2010
Stipulated Date of Completion /
Likely Date of Completion
August 20 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 3,59,76,814.81
Awarded for ₹ 3,25,13,771.00
 
Contractors
M/s. Rohini Industrial Electricals Ltd.
Consultants
M/s. Effective Architectural Services
5

Fire Fighting Works

100% completed
 
Project Duration
Stipulated Date of Commencement January 20 2011
Stipulated Date of Completion /
Likely Date of Completion
December 31 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 10,548,704.00
Awarded for ₹ 11,883,785.00
 
Contractors
M/s. Japsin Jacob Wire Drawing Pvt. Ltd..
Consultants
M/s. Effective Architectural Services
6

False ceiling work.

100% completed
 
Project Duration
Stipulated Date of Commencement February 19 2011
Stipulated Date of Completion /
Likely Date of Completion
September 30 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 16,123,055.00
Awarded for ₹ 13,112,071.90
 
Contractors
M/s. Concept Creator
Consultants
M/s. Effective Architectural Services
7

Sewage & Effluent Treatment Plant

100% completed
 
Project Duration
Stipulated Date of Commencement June 22 2011
Stipulated Date of Completion /
Likely Date of Completion
September 30 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 3,648,277.41
Awarded for ₹ 3,589,980.00
 
Contractors
M/s. Sombansi Enviro Engg. Pvt. Ltd.
Consultants
M/s. Effective Architectural Services
8

Air conditioning work.

100% completed
 
Project Duration
Stipulated Date of Commencement April 02 2011
Stipulated Date of Completion /
Likely Date of Completion
October 30 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 28,636,345.00
Awarded for ₹ 22,999,999.00
 
Contractors
M/s. Aprant Motors Pvt. Ltd.
Consultants
M/s. Effective Architectural Services
9

Lab furniture work

100% completed
 
Project Duration
Stipulated Date of Commencement December 15 2011
Stipulated Date of Completion /
Likely Date of Completion
June 30 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 48,287,670.00
Awarded for ₹ 29,652,470.00
 
Contractors
M/s. Godrej & Boyce Mfg. Co. Ltd.
Consultants
M/s. Effective Architectural Services
10

Gas piping work.

100% completed
 
Project Duration
Stipulated Date of Commencement February 27 2012
Stipulated Date of Completion /
Likely Date of Completion
September 30 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 21,417,128.15
Awarded for ₹ 20,297,433.80
 
Contractors
M/s. Steel Case
Consultants
M/s. Effective Architectural Services
11

Fumehood, Blowers and Ducting work

100% completed
 
Project Duration
Stipulated Date of Commencement April 19 2012
Stipulated Date of Completion /
Likely Date of Completion
September 30 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 35,214,351.00
Awarded for ₹ 18,028,622.54
 
Contractors
M/s. Steel Case
Consultants
M/s. Effective Architectural Services
12

Networking work

100% completed
 
Project Duration
Stipulated Date of Commencement September 19 2012
Stipulated Date of Completion /
Likely Date of Completion
September 06 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 10,352,655.95
Awarded for ₹ 7,145,532.34
 
Contractors
M/s. GMP Technology Solutions Pvt. Ltd
Consultants
M/s. Effective Architectural Services
13

Interior & Acoustic Work

100% completed
 
Project Duration
Stipulated Date of Commencement December 17 2012
Stipulated Date of Completion /
Likely Date of Completion
September 30 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 31,641,360.00
Awarded for ₹ 31,593,913.87
 
Contractors
M/s. T. S. Mistry
Consultants
M/s. Effective Architectural Services
14

Lab Accessories work.

100% completed
 
Project Duration
Stipulated Date of Commencement January 13 2013
Stipulated Date of Completion /
Likely Date of Completion
September 30 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 1,67,16,761.10
Awarded for ₹ 1,64,23,070.00
 
Contractors
M/s. Steel Case
Consultants
M/s. Effective Architectural Services
15

Bio Incubator : Civil & Plumbing works.

100% completed
 
Project Duration
Stipulated Date of Commencement October 06 2012
Stipulated Date of Completion /
Likely Date of Completion
Status
100%
Completed
Cost (₹)
Estimated at ₹ 12,016,258.00
Awarded for ₹ 13,083,870.45
 
Contractors
M/s. Indiana Build Infrastructure Pvt. Ltd.
Consultants
M/s. Effective Architectural Services

See Similar Projects

Upgradation and extension of existing Cottage Hospital at Chicalim, Goa SH: Office Furniture works

View Project

Interior work.

View Project