Project Duration
Stipulated Date of Commencement
September 29 2013
Actual Date of Completion
February 18 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 17,782,048.00
Awarded for
₹ 17,220,980.50
Final Cost of Project
₹ 19,543,125.16
Project highlights
Providing of loose furniture, false ceiling, panelling etc. in the the building.
Contractors
M/s. Floor Space
Consultants
M/S. FRISCHMANN PRABHU (INDIA) PVT. LTD.