Project Duration
Stipulated Date of Commencement January 25 2007
Actual Date of Completion April 15 2009
Status
100%
Completed
Cost (₹)
Estimated at ₹ 43,027,157.00
Awarded for ₹ 49,303,872.49
Final Cost of Project ₹ 38,546,072.00
 
Contractors
M/s. BGM Consortium Pvt. Ltd., M/s. BGM Consortium Pvt. Ltd.
Consultants
M/s. Effective Architectural Services, M/s. Effective Architectural Services
 