Status
Completed
Contractors
Consultants
Sub Works
This project involved 1 sub works. The details of the same available below
1
Construction of building at Patto with provision for Gas Insulated Sub Station, Panaji, Goa Phase I – Electrical Works
100% completed
Project Duration
Stipulated Date of Commencement
December 04 2021
Stipulated Date of Completion /
Likely Date of Completion June 03 2022
Likely Date of Completion June 03 2022
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,212,628.80
Awarded for
₹ 1,249,999.00
Project highlights
Electrification of Gas Insulated Sub Station Building
Contractors
M/s.Volton Engineering India Private Limited
Consultants
M/s. Vijaykumar Sawant & Associates
See Similar Projects
Design, manufacture, supply, installation, testing, commissioning and maintenance of elevators for various projects in Goa.
View Project
Cattle Breeding Farms – Copardem, Sattari, Goa – Under Rashtriya Krishi Vikas Yojana (10 sheds)
View Project
Urgent repairs of the existing lift in the building Essar Trade Centre, Morod, Mapusa, Bardez-Goa, wherein the office of Sub-registrar is situated
View Project