Project Duration
Stipulated Date of Commencement January 17 2018
Actual Date of Completion March 26 2018
Status
100%
Completed
Cost (₹)
Estimated at ₹ 571,048.00
Awarded for ₹ 597,920.00
Final Cost of Project ₹ 1,103,928.00

Project highlights

The scope of work includes dismantling of existing 33kV overhead lines and installation, testing & commissioning of 33 KV, 3C x 400 sq. mm, underground armored cable supplied by Goa Electricity Department.

 
Contractors
M/s. Pristine Engineering Services
Consultants
M/s. Rahul Deshpande
 