Project Duration
Stipulated Date of Commencement
May 31 2018
Stipulated Date of Completion /
Likely Date of Completion June 15 2023
Likely Date of Completion June 15 2023
Status
100%
Completed
Cost (₹)
Estimated at
₹ 95,573,993.00
Awarded for
₹ 82,304,576.29
Project highlights
Modular, carpentry & miscellaneous furniture
Contractors
M/s. T. S. Mistry,
Consultants
M/s. KICONS Limited