Project Duration
Stipulated Date of Commencement
May 26 2013
Stipulated Date of Completion /
Likely Date of Completion July 25 2013
Likely Date of Completion July 25 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 4,826,761.00
Awarded for
₹ 5,444,715.00
Project highlights
Construction of 25 decentralized community level composting stations and bin shelters at various locations within the Corporation of the City of Panaji.
Contractors
M/s. Abhiyant Infratech LLP
Consultants
In-house (GSIDC)