Project Duration
Stipulated Date of Commencement March 03 2007
Stipulated Date of Completion /
Likely Date of Completion
April 02 2009
Status
100%
Completed
Cost (₹)
Estimated at ₹ 174,969,028.00
Awarded for ₹ 186,209,408.98

Project highlights

RCC five storeyed building.
Ground Floor : Casualty ward & morgue, O.T.
First Floor : Consulting rooms.
Second Floor : Surgical wards, OT (04 nos.), ICU.
Third Floor : Pediatric wards, gynecology wards, antenatal ward, post natal wards, OT, special & twin private rooms.
Fourth Floor : Medicine Ward (Male & Female), ICCU, Conference Room.

 
Gallery Image
Contractors
M/s. IVRCL Infrastructure & Projects Ltd.
Gallery Image
Consultants
M/s. Intertek Architects & Consultants Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Upgradation of NICU at Goa Medical College, Bambolim-Goa – Office Furniture

View Project
Similar Project

Repairs to Library Block at Goa Medical College & Hospital at Bambolim, Goa – Interior & electrical work.

View Project
Similar Project

Maintenance work at Goa Medical College & Hospital and Health Centre’s under the jurisdiction of GMC, Bambolim, Goa- Exterior & Interior Painting Works

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.