Project Duration
Stipulated Date of Commencement
October 05 2006
Stipulated Date of Completion /
Likely Date of Completion November 13 2006
Likely Date of Completion November 13 2006
Status
100%
Completed
Cost (₹)
Estimated at
₹ 64,52.615.88
Awarded for
₹ 7,217,000.00
Project highlights
The work included supply and fixing of paver blocks, kerbs, ballusters, granite bollards, etc.
Contractors
M/s. Madanant Constructions (Goa) Pvt. Ltd.
Consultants
M/s. Construma Consultancy Pvt. Ltd.
See Similar Projects
Package III (VP Azossim-Mandur-Dongrim & VP Neura).
View Project
Civil and Plumbing works.
View Project
Construction of Washrooms at Mala in Panaji city- Package I
View Project