Project Duration
Stipulated Date of Commencement October 10 2014
Stipulated Date of Completion /
Likely Date of Completion
December 10 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 30,184,064.00
Awarded for ₹ 27,461,337.00

Project highlights

The scope of work invloves supply of decorative street light poles near Se Cathedral Church, Basilica of Bom Jesus and Mont Boa Vista at Old Goa