Project Duration
Stipulated Date of Commencement
October 22 2012
Stipulated Date of Completion /
Likely Date of Completion November 16 2012
Likely Date of Completion November 16 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 15,805,977.00
Awarded for
₹ 16,275,869.60
Project highlights
Repairs to foothpaths, benches, paiting of railings and kerbs from Divja circle to Dona Paula jetty in view of IFFI 2012.
Contractors
M/s. H. Candolkar & Sons
Consultants
M/s. Nilesh Salkar Associates