Project Duration
Stipulated Date of Commencement
June 23 2015
Stipulated Date of Completion /
Likely Date of Completion September 20 2015
Likely Date of Completion September 20 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 5,066,421.00
Awarded for
₹ 4,545,045.00
Project highlights
Air conditioning work
Contractors
M/s. Speedfrost Services Pvt. Ltd.
Consultants
M/s. Datta Kare Associates