Project Duration
Stipulated Date of Commencement
February 19 2010
Stipulated Date of Completion /
Likely Date of Completion June 18 2010
Likely Date of Completion June 18 2010
Status
100%
Completed
Cost (₹)
Estimated at
₹ 8,344,768.00
Awarded for
₹ 76,61,699.00
Contractors
M/s. Speedfrost Services
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.