Project Duration
Stipulated Date of Commencement
March 17 2022
Stipulated Date of Completion /
Likely Date of Completion June 16 2022
Likely Date of Completion June 16 2022
Status
100%
Completed
Cost (₹)
Estimated at
₹ 8,412,017.00
Awarded for
₹ 9,646,670.70
Project highlights
Additional works viz painting and other miscellaneous works in the new SCERT building
Contractors
M/s. Manup Infrastructures
Consultants
M/s. KICONS Ltd.