Project Duration
Stipulated Date of Commencement June 24 2022
Stipulated Date of Completion /
Likely Date of Completion
November 23 2022
Status
100%
Completed
Cost (₹)
Estimated at ₹ 11,066,766.80
Awarded for ₹ 13,903,408.51

Project highlights

Additional internal and external works in the new CHC premises

 
Gallery Image
Contractors
M/s. Sri Srinath Infra
Gallery Image
Consultants
M/s. Saolapurkar and Associates
 
Similar Projects

See Similar Projects

Similar Project

Air conditioning works

View Project
Similar Project

Renovation/Maintenance of Hospitals, CHCs, PHCs, RMDs under Directorate of Health Services in North Goa S.H.: Comprehensive Maintenance Contract for 2 No’s of Carrier make chillers (155TR each) for 3 Years at North Goa District Hospital, Mapusa.

View Project
Similar Project

Supply, Testing and Commissioning of Suction machine

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.