Project Duration
Stipulated Date of Commencement September 19 2011
Actual Date of Completion April 10 2012
Status
100%
Completed
Cost (₹)
Estimated at ₹ 6,575,575.00
Awarded for ₹ 4,886,125.00
 
Contractors
M/s. James Electrical
Consultants
M/s.Architecture Autonomous
 