Project Duration
Stipulated Date of Commencement
December 08 2009
Stipulated Date of Completion /
Likely Date of Completion December 27 2009
Likely Date of Completion December 27 2009
Status
100%
Completed
Cost (₹)
Estimated at
₹ 747,730.00
Awarded for
₹ 883,200.00
Contractors
M/s. Deshpande Constructions
Consultants
M/s. Architecture Autonomous / M/s. Mahimtura Consultants Pvt. Ltd.
See Similar Projects
Setting up of software technology park at Udyog Bhavan, Panaji, Goa- Dismantling civil and plumbing works
View Project
Construction of Panchayat Ghar at V.P Veling Priol- Cuncolim
View Project
Construction of Multipurpose Hall and office building for Village Panchayat, Salvador do Mundo – Phase I Land Development.
View Project





