प्रकल्प कालावधी
सुरू होण्याची ठराविक तारीख March 27 2007
पूर्ण होण्याची वास्तविक तारीख May 31 2013
स्थिती
100%
पूर्ण झालेले
किंमत (₹)
अंदाजे खर्च ₹ 203,081,980.00
ला देण्यात आला ₹ 228,194,428.00

प्रकल्पाची ठळक वैशिष्ट्ये

Science Faculty Building is conceptualized to meet the ever-growing needs of expansion of the campus to incorporate study of Science, for quality research facility and to create an excellent, modern research facility.
The work is completed in all respects at a cost of Rs. 48.00 Crore approximately and inaugurated on 13th May 2013.
The building is basement plus 2 storied RCC framed structure.
The built-up area is 20210.00 Sqm.
The structure is planned with three blocks AB block, C block and DE block, Where C block is joining of two wings AB and DE having main entrance at the Ground floor and Library and offices on upper floors. AB Block and DE block comprises lecture hall, research lab and administration spaces.
The building comprises of two seminar halls. One in AB block having capacity of 180 No chairs and other in DE block having capacity of 325 No chairs.
There are four central open courtyards for natural light and ventilation into the rooms.
The building has six staircase blocks designed for public circulation and one internal staircase in the library. All the staircases are well equipped for fire escape. Also 4 Nos. of lifts are provided.
Building is well equipped with fire fighting equipments, networking facilities, lab furniture, fume hoods in labs, gas piping in labs, interior & acoustic, furniture, etc.
All the floors are provided with adequate toilet facilities, etc.
Parking facilities for four wheelers and two wheelers, RCC road, landscaping, STP & ETP, Gas Bank, Pump room etc.

 
Gallery Image
कंत्राटदार
M/s. D. S. Contractors Private Limited
Gallery Image
सल्लागार
M/s. Effective Architectural Services
 

उप कामे

या प्रकल्पात 14 उप कामाचा समावेश होता. त्याचा तपशील खाली उपलब्ध आहे.

1

Lifts / Elevator work.

100% पूर्ण झालेले
 
प्रकल्प कालावधी
सुरू होण्याची ठराविक तारीख October 05 2009
पूर्ण होण्याची वास्तविक तारीख April 30 2013
स्थिती
100%
पूर्ण झालेले
किंमत (₹)
अंदाजे खर्च ₹ 2,450,000.00
ला देण्यात आला ₹ 2,570,000.00
 
Contractors
कंत्राटदार
M/s. Thyssenkrupp Elevator (India) Pvt. Ltd.
Consultants
सल्लागार
M/s. Effective Architectural Services
2

Structural Steel, Roofing and Structural Glazing works

100% पूर्ण झालेले
 
प्रकल्प कालावधी
सुरू होण्याची ठराविक तारीख August 14 2010
पूर्ण होण्याची वास्तविक तारीख April 30 2012
स्थिती
100%
पूर्ण झालेले
किंमत (₹)
अंदाजे खर्च ₹ 17,300,928.00
ला देण्यात आला ₹ 16,920,811.16
 
Contractors
कंत्राटदार
M/s. D. S. Contractors Private Limited
Consultants
सल्लागार
M/s. Effective Architectural Services
3

External Electrical work

100% पूर्ण झालेले
 
प्रकल्प कालावधी
सुरू होण्याची ठराविक तारीख November 27 2010
पूर्ण होण्याची वास्तविक तारीख August 20 2013
स्थिती
100%
पूर्ण झालेले
किंमत (₹)
अंदाजे खर्च ₹ 3,59,76,814.81
ला देण्यात आला ₹ 3,25,13,771.00
 
Contractors
कंत्राटदार
M/s. Rohini Industrial Electricals Ltd.
Consultants
सल्लागार
M/s. Effective Architectural Services
4

Fire Fighting Works

100% पूर्ण झालेले
 
प्रकल्प कालावधी
सुरू होण्याची ठराविक तारीख January 20 2011
पूर्ण होण्याची वास्तविक तारीख December 31 2013
स्थिती
100%
पूर्ण झालेले
किंमत (₹)
अंदाजे खर्च ₹ 10,548,704.00
ला देण्यात आला ₹ 11,883,785.00
 
Contractors
कंत्राटदार
M/s. Japsin Jacob Wire Drawing Pvt. Ltd..
Consultants
सल्लागार
M/s. Effective Architectural Services
5

False ceiling work.

100% पूर्ण झालेले
 
प्रकल्प कालावधी
सुरू होण्याची ठराविक तारीख February 19 2011
पूर्ण होण्याची वास्तविक तारीख April 30 2013
स्थिती
100%
पूर्ण झालेले
किंमत (₹)
अंदाजे खर्च ₹ 16,123,055.00
ला देण्यात आला ₹ 13,112,071.90
 
Contractors
कंत्राटदार
M/s. Concept Creators
Consultants
सल्लागार
M/s. Effective Architectural Services
6

Sewage & Effluent Treatment Plant

100% पूर्ण झालेले
 
प्रकल्प कालावधी
सुरू होण्याची ठराविक तारीख June 22 2011
पूर्ण होण्याची वास्तविक तारीख September 20 2013
स्थिती
100%
पूर्ण झालेले
किंमत (₹)
अंदाजे खर्च ₹ 3,648,277.41
ला देण्यात आला ₹ 3,589,980.00
 
Contractors
कंत्राटदार
M/s. Sombansi Enviro Engg. Pvt. Ltd.
Consultants
सल्लागार
M/s. Effective Architectural Services
7

Air conditioning work.

100% पूर्ण झालेले
 
प्रकल्प कालावधी
सुरू होण्याची ठराविक तारीख April 02 2011
पूर्ण होण्याची वास्तविक तारीख October 30 2013
स्थिती
100%
पूर्ण झालेले
किंमत (₹)
अंदाजे खर्च ₹ 28,636,345.00
ला देण्यात आला ₹ 22,999,999.00
 
Contractors
कंत्राटदार
M/s. Aprant Motors Pvt. Ltd.
Consultants
सल्लागार
M/s. Effective Architectural Services
8

Lab furniture work

100% पूर्ण झालेले
 
प्रकल्प कालावधी
सुरू होण्याची ठराविक तारीख December 15 2011
पूर्ण होण्याची वास्तविक तारीख June 30 2013
स्थिती
100%
पूर्ण झालेले
किंमत (₹)
अंदाजे खर्च ₹ 48,287,670.00
ला देण्यात आला ₹ 29,652,470.00
 
Contractors
कंत्राटदार
M/s. Godrej & Boyce Mfg. Co. Ltd.
Consultants
सल्लागार
M/s. Effective Architectural Services
9

Gas piping work.

100% पूर्ण झालेले
 
प्रकल्प कालावधी
सुरू होण्याची ठराविक तारीख February 27 2012
पूर्ण होण्याची वास्तविक तारीख April 30 2013
स्थिती
100%
पूर्ण झालेले
किंमत (₹)
अंदाजे खर्च ₹ 21,417,128.15
ला देण्यात आला ₹ 20,297,433.80
 
Contractors
कंत्राटदार
M/s. Steel Case
Consultants
सल्लागार
M/s. Effective Architectural Services
10

Fumehood, Blowers and Ducting work

100% पूर्ण झालेले
 
प्रकल्प कालावधी
सुरू होण्याची ठराविक तारीख April 19 2012
पूर्ण होण्याची वास्तविक तारीख April 30 2013
स्थिती
100%
पूर्ण झालेले
किंमत (₹)
अंदाजे खर्च ₹ 35,214,351.00
ला देण्यात आला ₹ 18,028,622.54
 
Contractors
कंत्राटदार
M/s. Steel Case
Consultants
सल्लागार
M/s. Effective Architectural Services
11

Networking work

100% पूर्ण झालेले
 
प्रकल्प कालावधी
सुरू होण्याची ठराविक तारीख September 19 2012
पूर्ण होण्याची वास्तविक तारीख September 06 2013
स्थिती
100%
पूर्ण झालेले
किंमत (₹)
अंदाजे खर्च ₹ 10,352,655.95
ला देण्यात आला ₹ 7,145,532.34
 
Contractors
कंत्राटदार
M/s. GMP Technology Solutions Pvt. Ltd
Consultants
सल्लागार
M/s. Effective Architectural Services
12

Interior & Acoustic Work

100% पूर्ण झालेले
 
प्रकल्प कालावधी
सुरू होण्याची ठराविक तारीख December 17 2012
पूर्ण होण्याची वास्तविक तारीख October 21 2013
स्थिती
100%
पूर्ण झालेले
किंमत (₹)
अंदाजे खर्च ₹ 31,641,360.00
ला देण्यात आला ₹ 31,593,913.87
 
Contractors
कंत्राटदार
M/s. T. S. Mistry
Consultants
सल्लागार
M/s. Effective Architectural Services
13

Lab Accessories work.

100% पूर्ण झालेले
 
प्रकल्प कालावधी
सुरू होण्याची ठराविक तारीख January 13 2013
पूर्ण होण्याची वास्तविक तारीख April 30 2013
स्थिती
100%
पूर्ण झालेले
किंमत (₹)
अंदाजे खर्च ₹ 1,67,16,761.10
ला देण्यात आला ₹ 1,64,23,070.00
 
Contractors
कंत्राटदार
M/s. Steel Case
Consultants
सल्लागार
M/s. Effective Architectural Services
14

Bio Incubator : Civil & Plumbing works.

100% पूर्ण झालेले
 
प्रकल्प कालावधी
सुरू होण्याची ठराविक तारीख October 09 2012
पूर्ण होण्याची वास्तविक तारीख
स्थिती
100%
पूर्ण झालेले
किंमत (₹)
अंदाजे खर्च ₹ 12,016,258.00
ला देण्यात आला ₹ 13,083,870.45

प्रकल्पाची ठळक वैशिष्ट्ये

Foreclosed.
GSIDC in its 124th Board Meeting held on 28th November 2013, vide Resolution No.3367, resolved to foreclose the Contract of M/s. Indiana Build Infrastructure Pvt. Ltd.

 
Contractors
कंत्राटदार
M/s. Indiana Build Infrastructure Pvt. Ltd.
Consultants
सल्लागार
M/s. Effective Architectural Services
Similar Projects

यासारखे प्रकल्प बघा

Similar Project

Construction of seed processing and storage unit building at Ella, Old Goa.

तपशील पहा
Similar Project

Construction of Yojana Bhavan for Directorate of Planning, Statistics & Evaluation at Porvorim, Goa – Additional works

तपशील पहा
Similar Project

Restoration of old Government Secretariat Building at Panaji, Goa to make it a Centre of Art and Culture- civil, plumbing & Electrical work

तपशील पहा
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
अस्वीकरण: राजभाषा संचालनालय, गोवा सरकार द्वारे अनुवादित. टीप: कोणत्याही परिस्थितीत कायदेशीर अर्थाविष्कारासाठी, इंग्रजी आवृत्तीला प्राधान्य दिले जाईल.