Construction of Building for Science Faculty at Goa University, Taleigao, Tiswadi Goa
– Civil, electrification & land development work.
प्रकल्प कालावधी
सुरू होण्याची ठराविक तारीखMarch 27 2007
पूर्ण होण्याची वास्तविक तारीखMay 31 2013
स्थिती
100%
पूर्ण झालेले
किंमत (₹)
अंदाजे खर्च₹ 203,081,980.00
ला देण्यात आला₹ 228,194,428.00
प्रकल्पाची ठळक वैशिष्ट्ये
Science Faculty Building is conceptualized to meet the ever-growing needs of expansion of the campus to incorporate study of Science, for quality research facility and to create an excellent, modern research facility.
The work is completed in all respects at a cost of Rs. 48.00 Crore approximately and inaugurated on 13th May 2013.
The building is basement plus 2 storied RCC framed structure.
The built-up area is 20210.00 Sqm.
The structure is planned with three blocks AB block, C block and DE block, Where C block is joining of two wings AB and DE having main entrance at the Ground floor and Library and offices on upper floors. AB Block and DE block comprises lecture hall, research lab and administration spaces.
The building comprises of two seminar halls. One in AB block having capacity of 180 No chairs and other in DE block having capacity of 325 No chairs.
There are four central open courtyards for natural light and ventilation into the rooms.
The building has six staircase blocks designed for public circulation and one internal staircase in the library. All the staircases are well equipped for fire escape. Also 4 Nos. of lifts are provided.
Building is well equipped with fire fighting equipments, networking facilities, lab furniture, fume hoods in labs, gas piping in labs, interior & acoustic, furniture, etc.
All the floors are provided with adequate toilet facilities, etc.
Parking facilities for four wheelers and two wheelers, RCC road, landscaping, STP & ETP, Gas Bank, Pump room etc.
कंत्राटदार
M/s. D. S. Contractors Private Limited
सल्लागार
M/s. Effective Architectural Services
उप कामे
या प्रकल्पात 14 उप कामाचा समावेश होता. त्याचा तपशील खाली उपलब्ध आहे.
1
Lifts / Elevator work.
100% पूर्ण झालेले
प्रकल्प कालावधी
सुरू होण्याची ठराविक तारीख October 05 2009
पूर्ण होण्याची वास्तविक तारीख April 30 2013
स्थिती
100%
पूर्ण झालेले
किंमत (₹)
अंदाजे खर्च₹ 2,450,000.00
ला देण्यात आला₹ 2,570,000.00
कंत्राटदार
M/s. Thyssenkrupp Elevator (India) Pvt. Ltd.
सल्लागार
M/s. Effective Architectural Services
2
Structural Steel, Roofing and Structural Glazing works
100% पूर्ण झालेले
प्रकल्प कालावधी
सुरू होण्याची ठराविक तारीख August 14 2010
पूर्ण होण्याची वास्तविक तारीख April 30 2012
स्थिती
100%
पूर्ण झालेले
किंमत (₹)
अंदाजे खर्च₹ 17,300,928.00
ला देण्यात आला₹ 16,920,811.16
कंत्राटदार
M/s. D. S. Contractors Private Limited
सल्लागार
M/s. Effective Architectural Services
3
External Electrical work
100% पूर्ण झालेले
प्रकल्प कालावधी
सुरू होण्याची ठराविक तारीख November 27 2010
पूर्ण होण्याची वास्तविक तारीख August 20 2013
स्थिती
100%
पूर्ण झालेले
किंमत (₹)
अंदाजे खर्च₹ 3,59,76,814.81
ला देण्यात आला₹ 3,25,13,771.00
कंत्राटदार
M/s. Rohini Industrial Electricals Ltd.
सल्लागार
M/s. Effective Architectural Services
4
Fire Fighting Works
100% पूर्ण झालेले
प्रकल्प कालावधी
सुरू होण्याची ठराविक तारीख January 20 2011
पूर्ण होण्याची वास्तविक तारीख December 31 2013
स्थिती
100%
पूर्ण झालेले
किंमत (₹)
अंदाजे खर्च₹ 10,548,704.00
ला देण्यात आला₹ 11,883,785.00
कंत्राटदार
M/s. Japsin Jacob Wire Drawing Pvt. Ltd..
सल्लागार
M/s. Effective Architectural Services
5
False ceiling work.
100% पूर्ण झालेले
प्रकल्प कालावधी
सुरू होण्याची ठराविक तारीख February 19 2011
पूर्ण होण्याची वास्तविक तारीख April 30 2013
स्थिती
100%
पूर्ण झालेले
किंमत (₹)
अंदाजे खर्च₹ 16,123,055.00
ला देण्यात आला₹ 13,112,071.90
कंत्राटदार
M/s. Concept Creators
सल्लागार
M/s. Effective Architectural Services
6
Sewage & Effluent Treatment Plant
100% पूर्ण झालेले
प्रकल्प कालावधी
सुरू होण्याची ठराविक तारीख June 22 2011
पूर्ण होण्याची वास्तविक तारीख September 20 2013
स्थिती
100%
पूर्ण झालेले
किंमत (₹)
अंदाजे खर्च₹ 3,648,277.41
ला देण्यात आला₹ 3,589,980.00
कंत्राटदार
M/s. Sombansi Enviro Engg. Pvt. Ltd.
सल्लागार
M/s. Effective Architectural Services
7
Air conditioning work.
100% पूर्ण झालेले
प्रकल्प कालावधी
सुरू होण्याची ठराविक तारीख April 02 2011
पूर्ण होण्याची वास्तविक तारीख October 30 2013
स्थिती
100%
पूर्ण झालेले
किंमत (₹)
अंदाजे खर्च₹ 28,636,345.00
ला देण्यात आला₹ 22,999,999.00
कंत्राटदार
M/s. Aprant Motors Pvt. Ltd.
सल्लागार
M/s. Effective Architectural Services
8
Lab furniture work
100% पूर्ण झालेले
प्रकल्प कालावधी
सुरू होण्याची ठराविक तारीख December 15 2011
पूर्ण होण्याची वास्तविक तारीख June 30 2013
स्थिती
100%
पूर्ण झालेले
किंमत (₹)
अंदाजे खर्च₹ 48,287,670.00
ला देण्यात आला₹ 29,652,470.00
कंत्राटदार
M/s. Godrej & Boyce Mfg. Co. Ltd.
सल्लागार
M/s. Effective Architectural Services
9
Gas piping work.
100% पूर्ण झालेले
प्रकल्प कालावधी
सुरू होण्याची ठराविक तारीख February 27 2012
पूर्ण होण्याची वास्तविक तारीख April 30 2013
स्थिती
100%
पूर्ण झालेले
किंमत (₹)
अंदाजे खर्च₹ 21,417,128.15
ला देण्यात आला₹ 20,297,433.80
कंत्राटदार
M/s. Steel Case
सल्लागार
M/s. Effective Architectural Services
10
Fumehood, Blowers and Ducting work
100% पूर्ण झालेले
प्रकल्प कालावधी
सुरू होण्याची ठराविक तारीख April 19 2012
पूर्ण होण्याची वास्तविक तारीख April 30 2013
स्थिती
100%
पूर्ण झालेले
किंमत (₹)
अंदाजे खर्च₹ 35,214,351.00
ला देण्यात आला₹ 18,028,622.54
कंत्राटदार
M/s. Steel Case
सल्लागार
M/s. Effective Architectural Services
11
Networking work
100% पूर्ण झालेले
प्रकल्प कालावधी
सुरू होण्याची ठराविक तारीख September 19 2012
पूर्ण होण्याची वास्तविक तारीख September 06 2013
स्थिती
100%
पूर्ण झालेले
किंमत (₹)
अंदाजे खर्च₹ 10,352,655.95
ला देण्यात आला₹ 7,145,532.34
कंत्राटदार
M/s. GMP Technology Solutions Pvt. Ltd
सल्लागार
M/s. Effective Architectural Services
12
Interior & Acoustic Work
100% पूर्ण झालेले
प्रकल्प कालावधी
सुरू होण्याची ठराविक तारीख December 17 2012
पूर्ण होण्याची वास्तविक तारीख October 21 2013
स्थिती
100%
पूर्ण झालेले
किंमत (₹)
अंदाजे खर्च₹ 31,641,360.00
ला देण्यात आला₹ 31,593,913.87
कंत्राटदार
M/s. T. S. Mistry
सल्लागार
M/s. Effective Architectural Services
13
Lab Accessories work.
100% पूर्ण झालेले
प्रकल्प कालावधी
सुरू होण्याची ठराविक तारीख January 13 2013
पूर्ण होण्याची वास्तविक तारीख April 30 2013
स्थिती
100%
पूर्ण झालेले
किंमत (₹)
अंदाजे खर्च₹ 1,67,16,761.10
ला देण्यात आला₹ 1,64,23,070.00
कंत्राटदार
M/s. Steel Case
सल्लागार
M/s. Effective Architectural Services
14
Bio Incubator : Civil & Plumbing works.
100% पूर्ण झालेले
प्रकल्प कालावधी
सुरू होण्याची ठराविक तारीख October 09 2012
पूर्ण होण्याची वास्तविक तारीख
स्थिती
100%
पूर्ण झालेले
किंमत (₹)
अंदाजे खर्च₹ 12,016,258.00
ला देण्यात आला₹ 13,083,870.45
प्रकल्पाची ठळक वैशिष्ट्ये
Foreclosed.
GSIDC in its 124th Board Meeting held on 28th November 2013, vide Resolution No.3367, resolved to foreclose the Contract of M/s. Indiana Build Infrastructure Pvt. Ltd.