प्रकल्प कालावधी
सुरू होण्याची ठराविक तारीख March 07 2019
पूर्ण होण्याची वास्तविक तारीख March 05 2022
स्थिती
100%
पूर्ण झालेले
किंमत (₹)
अंदाजे खर्च ₹ 175,332,406.41
ला देण्यात आला ₹ 197038617.4

प्रकल्पाची ठळक वैशिष्ट्ये

The planning of the Bus-Stand is on a hexagonal grid; the hexagon is appropriately scaled to accommodate varied facilities.The Bus stand has seperate entry & exit gates with 10 no.s of alighting & departing bays and 6no.s of waiting bays.Pedestrian movement within the bus-stand has been given greatest priority – with complete segregation of pedestrian & vehicular movement. A barrier free environment is provided for the bus-stand commuters. Public conveniences (ticketing counters, 10 no.s of shops & a canteen) have been provided at the lower level. The community hall has been located on the upper floor. The public spaces as well as enclosed spaces thrive on natural light and ventilation. The rear side of the property is provided with a Mini Depot for the interstate buses with admin offices.

 
Gallery Image
कंत्राटदार
M/s. Shreejikrupa Buildcon Ltd
Gallery Image
सल्लागार
M/s. UCJ Architecture & Environment
 

उप कामे

या प्रकल्पात 1 उप कामाचा समावेश होता. त्याचा तपशील खाली उपलब्ध आहे.

1

Construction of Bus Stand & Mini Depot at Sankhali, Goa – Erection of 11KV line from Electricity Department feeder to bus stand substation.

100% पूर्ण झालेले
 
प्रकल्प कालावधी
सुरू होण्याची ठराविक तारीख January 05 2022
पूर्ण होण्याची वास्तविक तारीख April 24 2022
स्थिती
100%
पूर्ण झालेले
किंमत (₹)
अंदाजे खर्च ₹ 1,899,896.00
ला देण्यात आला ₹ 1,880,600.20

प्रकल्पाची ठळक वैशिष्ट्ये

Erection of 11KV line from Electricity Department feeder to bus stand substation.

 
Contractors
कंत्राटदार
M/s. Volton Engineering (I) Pvt. Ltd.,
Consultants
सल्लागार
M/s UCJ Architecture & Environment
Similar Projects

यासारखे प्रकल्प बघा

Similar Project

Construction of Poriem Bridge including approaches.

तपशील पहा
Similar Project

Improvement and Upgradation of road network from MDLB Hospital to Baina Sea Shore, Shafi Masjid to Baina Recreational Club, Bharat lines to Headland Sada Junction in Mormugao Constituency.

तपशील पहा
Similar Project

St. Inez Creek Barricading

तपशील पहा
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
अस्वीकरण: राजभाषा संचालनालय, गोवा सरकार द्वारे अनुवादित. टीप: कोणत्याही परिस्थितीत कायदेशीर अर्थाविष्कारासाठी, इंग्रजी आवृत्तीला प्राधान्य दिले जाईल.