प्रकल्पाची कालावधी
सुरवात जावपाची थारायल्ली तारीख March 27 2007
पुराय जावपाची प्रत्यक्ष तारीख May 31 2013
स्थिती
100%
पुराय जाल्ले
खर्च (₹)
अदमास खर्च ₹ 203,081,980.00
दिले ₹ 228,194,428.00

प्रकल्प हायलायट्स

Science Faculty Building is conceptualized to meet the ever-growing needs of expansion of the campus to incorporate study of Science, for quality research facility and to create an excellent, modern research facility.
The work is completed in all respects at a cost of Rs. 48.00 Crore approximately and inaugurated on 13th May 2013.
The building is basement plus 2 storied RCC framed structure.
The built-up area is 20210.00 Sqm.
The structure is planned with three blocks AB block, C block and DE block, Where C block is joining of two wings AB and DE having main entrance at the Ground floor and Library and offices on upper floors. AB Block and DE block comprises lecture hall, research lab and administration spaces.
The building comprises of two seminar halls. One in AB block having capacity of 180 No chairs and other in DE block having capacity of 325 No chairs.
There are four central open courtyards for natural light and ventilation into the rooms.
The building has six staircase blocks designed for public circulation and one internal staircase in the library. All the staircases are well equipped for fire escape. Also 4 Nos. of lifts are provided.
Building is well equipped with fire fighting equipments, networking facilities, lab furniture, fume hoods in labs, gas piping in labs, interior & acoustic, furniture, etc.
All the floors are provided with adequate toilet facilities, etc.
Parking facilities for four wheelers and two wheelers, RCC road, landscaping, STP & ETP, Gas Bank, Pump room etc.

 
Gallery Image
कंत्राटदार
M/s. D. S. Contractors Private Limited
Gallery Image
सल्लागार
M/s. Effective Architectural Services
 

उप-काम

ह्या प्रकल्पांत 14 उप-कामांचो आसपाव आसा. हाचो तपशील सकयल उपलब्ध आसा.

1

Lifts / Elevator work.

100% पुराय जाल्ले
 
प्रकल्पाची कालावधी
सुरवात जावपाची थारायल्ली तारीख October 05 2009
पुराय जावपाची प्रत्यक्ष तारीख April 30 2013
स्थिती
100%
पुराय जाल्ले
खर्च (₹)
अदमास खर्च ₹ 2,450,000.00
दिले ₹ 2,570,000.00
 
Contractors
कंत्राटदार
M/s. Thyssenkrupp Elevator (India) Pvt. Ltd.
Consultants
सल्लागार
M/s. Effective Architectural Services
2

Structural Steel, Roofing and Structural Glazing works

100% पुराय जाल्ले
 
प्रकल्पाची कालावधी
सुरवात जावपाची थारायल्ली तारीख August 14 2010
पुराय जावपाची प्रत्यक्ष तारीख April 30 2012
स्थिती
100%
पुराय जाल्ले
खर्च (₹)
अदमास खर्च ₹ 17,300,928.00
दिले ₹ 16,920,811.16
 
Contractors
कंत्राटदार
M/s. D. S. Contractors Private Limited
Consultants
सल्लागार
M/s. Effective Architectural Services
3

External Electrical work

100% पुराय जाल्ले
 
प्रकल्पाची कालावधी
सुरवात जावपाची थारायल्ली तारीख November 27 2010
पुराय जावपाची प्रत्यक्ष तारीख August 20 2013
स्थिती
100%
पुराय जाल्ले
खर्च (₹)
अदमास खर्च ₹ 3,59,76,814.81
दिले ₹ 3,25,13,771.00
 
Contractors
कंत्राटदार
M/s. Rohini Industrial Electricals Ltd.
Consultants
सल्लागार
M/s. Effective Architectural Services
4

Fire Fighting Works

100% पुराय जाल्ले
 
प्रकल्पाची कालावधी
सुरवात जावपाची थारायल्ली तारीख January 20 2011
पुराय जावपाची प्रत्यक्ष तारीख December 31 2013
स्थिती
100%
पुराय जाल्ले
खर्च (₹)
अदमास खर्च ₹ 10,548,704.00
दिले ₹ 11,883,785.00
 
Contractors
कंत्राटदार
M/s. Japsin Jacob Wire Drawing Pvt. Ltd..
Consultants
सल्लागार
M/s. Effective Architectural Services
5

False ceiling work.

100% पुराय जाल्ले
 
प्रकल्पाची कालावधी
सुरवात जावपाची थारायल्ली तारीख February 19 2011
पुराय जावपाची प्रत्यक्ष तारीख April 30 2013
स्थिती
100%
पुराय जाल्ले
खर्च (₹)
अदमास खर्च ₹ 16,123,055.00
दिले ₹ 13,112,071.90
 
Contractors
कंत्राटदार
M/s. Concept Creators
Consultants
सल्लागार
M/s. Effective Architectural Services
6

Sewage & Effluent Treatment Plant

100% पुराय जाल्ले
 
प्रकल्पाची कालावधी
सुरवात जावपाची थारायल्ली तारीख June 22 2011
पुराय जावपाची प्रत्यक्ष तारीख September 20 2013
स्थिती
100%
पुराय जाल्ले
खर्च (₹)
अदमास खर्च ₹ 3,648,277.41
दिले ₹ 3,589,980.00
 
Contractors
कंत्राटदार
M/s. Sombansi Enviro Engg. Pvt. Ltd.
Consultants
सल्लागार
M/s. Effective Architectural Services
7

Air conditioning work.

100% पुराय जाल्ले
 
प्रकल्पाची कालावधी
सुरवात जावपाची थारायल्ली तारीख April 02 2011
पुराय जावपाची प्रत्यक्ष तारीख October 30 2013
स्थिती
100%
पुराय जाल्ले
खर्च (₹)
अदमास खर्च ₹ 28,636,345.00
दिले ₹ 22,999,999.00
 
Contractors
कंत्राटदार
M/s. Aprant Motors Pvt. Ltd.
Consultants
सल्लागार
M/s. Effective Architectural Services
8

Lab furniture work

100% पुराय जाल्ले
 
प्रकल्पाची कालावधी
सुरवात जावपाची थारायल्ली तारीख December 15 2011
पुराय जावपाची प्रत्यक्ष तारीख June 30 2013
स्थिती
100%
पुराय जाल्ले
खर्च (₹)
अदमास खर्च ₹ 48,287,670.00
दिले ₹ 29,652,470.00
 
Contractors
कंत्राटदार
M/s. Godrej & Boyce Mfg. Co. Ltd.
Consultants
सल्लागार
M/s. Effective Architectural Services
9

Gas piping work.

100% पुराय जाल्ले
 
प्रकल्पाची कालावधी
सुरवात जावपाची थारायल्ली तारीख February 27 2012
पुराय जावपाची प्रत्यक्ष तारीख April 30 2013
स्थिती
100%
पुराय जाल्ले
खर्च (₹)
अदमास खर्च ₹ 21,417,128.15
दिले ₹ 20,297,433.80
 
Contractors
कंत्राटदार
M/s. Steel Case
Consultants
सल्लागार
M/s. Effective Architectural Services
10

Fumehood, Blowers and Ducting work

100% पुराय जाल्ले
 
प्रकल्पाची कालावधी
सुरवात जावपाची थारायल्ली तारीख April 19 2012
पुराय जावपाची प्रत्यक्ष तारीख April 30 2013
स्थिती
100%
पुराय जाल्ले
खर्च (₹)
अदमास खर्च ₹ 35,214,351.00
दिले ₹ 18,028,622.54
 
Contractors
कंत्राटदार
M/s. Steel Case
Consultants
सल्लागार
M/s. Effective Architectural Services
11

Networking work

100% पुराय जाल्ले
 
प्रकल्पाची कालावधी
सुरवात जावपाची थारायल्ली तारीख September 19 2012
पुराय जावपाची प्रत्यक्ष तारीख September 06 2013
स्थिती
100%
पुराय जाल्ले
खर्च (₹)
अदमास खर्च ₹ 10,352,655.95
दिले ₹ 7,145,532.34
 
Contractors
कंत्राटदार
M/s. GMP Technology Solutions Pvt. Ltd
Consultants
सल्लागार
M/s. Effective Architectural Services
12

Interior & Acoustic Work

100% पुराय जाल्ले
 
प्रकल्पाची कालावधी
सुरवात जावपाची थारायल्ली तारीख December 17 2012
पुराय जावपाची प्रत्यक्ष तारीख October 21 2013
स्थिती
100%
पुराय जाल्ले
खर्च (₹)
अदमास खर्च ₹ 31,641,360.00
दिले ₹ 31,593,913.87
 
Contractors
कंत्राटदार
M/s. T. S. Mistry
Consultants
सल्लागार
M/s. Effective Architectural Services
13

Lab Accessories work.

100% पुराय जाल्ले
 
प्रकल्पाची कालावधी
सुरवात जावपाची थारायल्ली तारीख January 13 2013
पुराय जावपाची प्रत्यक्ष तारीख April 30 2013
स्थिती
100%
पुराय जाल्ले
खर्च (₹)
अदमास खर्च ₹ 1,67,16,761.10
दिले ₹ 1,64,23,070.00
 
Contractors
कंत्राटदार
M/s. Steel Case
Consultants
सल्लागार
M/s. Effective Architectural Services
14

Bio Incubator : Civil & Plumbing works.

100% पुराय जाल्ले
 
प्रकल्पाची कालावधी
सुरवात जावपाची थारायल्ली तारीख October 09 2012
पुराय जावपाची प्रत्यक्ष तारीख
स्थिती
100%
पुराय जाल्ले
खर्च (₹)
अदमास खर्च ₹ 12,016,258.00
दिले ₹ 13,083,870.45

प्रकल्प हायलायट्स

Foreclosed.
GSIDC in its 124th Board Meeting held on 28th November 2013, vide Resolution No.3367, resolved to foreclose the Contract of M/s. Indiana Build Infrastructure Pvt. Ltd.

 
Contractors
कंत्राटदार
M/s. Indiana Build Infrastructure Pvt. Ltd.
Consultants
सल्लागार
M/s. Effective Architectural Services
Similar Projects

अशेच तरेचे प्रकल्प पळोवचे

Similar Project

Development of 20 point programme sites at the villages of Podocem in Sattari Taluka.

तपशील पळोवचे
Similar Project

Painting of Breda Pillars at Divja Circle, Panaji, Goa – Paint application.

तपशील पळोवचे
Similar Project

Refurbishment of Maquinez Palace, Maquinezuinez Palace Annex and Old GMC Building for IFFI 2017 -Electrical Works.

तपशील पळोवचे
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
अस्विकरण: राजभाशा संचालनालय, गोंय सरकारा वरवीं अणकारीत. टीप: खंयचेय स्थितींत कायदेशीर अर्थावणी खातीर इंग्लीश आवृत्तीक प्राधान्य दितले.