प्रकल्पाची कालावधी
सुरवात जावपाची थारायल्ली तारीख December 27 2015
पुराय जावपाची प्रत्यक्ष तारीख April 30 2021
स्थिती
100%
पुराय जाल्ले
खर्च (₹)
अदमास खर्च ₹ 834,975,942.53
दिले ₹ 996,008,692.20

प्रकल्प हायलायट्स

Main Building
Basement:
• CSO (Central Stores office) & Pharmacy store
• Laundry, Stores &maintenance workshops & Parking space
Ground Floor:
• 21 OPD Clinics, Casualty with minor Operation Theatre,
• Diagnostics, Imaging suite, Physiotherapy, Blood Bank, Laboratory
• CSSD (Central Supply Stores Department), IPD Kitchen etc.
First Floor:
• 7 Operation Theatres with Pre & Post-Operative Room, Surgery, ENT IPD ward, Burns ward, Prisoners’ ward etc.
Second Floor:
• Administrative block, 3 OT, Obstetrics & Gynecology and Pediatric IPD wards, NICU (Neonatal Intensive Care Unit), PICU (Pediatric Intensive Care Unit)
Third Floor:
• MICU, ICU, Dialysis, Psychiatry, Medicine, IPD wards
Mortuary Building
• Morgue for 72 cabinets, Autopsy Room, Embalming Room, Waiting, Doctors Rooms, Post Mortem Room etc.
Utility Building
• Transformers, Electrical panel room Chiller system, Water Filtration system, Hot water tanks
• Underground water tanks for raw water, domestic water, soft water and fire water.
• D. G. sets outside

 
Gallery Image
कंत्राटदार
M/s. Parnika Commercial & Estates P. Ltd
Gallery Image
सल्लागार
M/s. KICONS Limited
 

उप-काम

ह्या प्रकल्पांत 11 उप-कामांचो आसपाव आसा. हाचो तपशील सकयल उपलब्ध आसा.

1

False ceiling work.

100% पुराय जाल्ले
 
प्रकल्पाची कालावधी
सुरवात जावपाची थारायल्ली तारीख December 30 2016
पुराय जावपाची प्रत्यक्ष तारीख April 15 2021
स्थिती
100%
पुराय जाल्ले
खर्च (₹)
अदमास खर्च ₹ 69,812,937.00
दिले ₹ 60,183,352.75

प्रकल्प हायलायट्स

Metal False Ceiling, Calcium silicate false ceiling work

 
Contractors
कंत्राटदार
M/s. Deshpande Constructions
Consultants
सल्लागार
M/s. KICONS Limited
2

Interior work

100% पुराय जाल्ले
 
प्रकल्पाची कालावधी
सुरवात जावपाची थारायल्ली तारीख May 31 2018
पुराय जावपाची प्रत्यक्ष तारीख June 15 2023
स्थिती
100%
पुराय जाल्ले
खर्च (₹)
अदमास खर्च ₹ 95,573,993.00
दिले ₹ 82,304,576.29

प्रकल्प हायलायट्स

Modular, carpentry & miscellaneous furniture

 
Contractors
कंत्राटदार
M/s. T. S. Mistry,
Consultants
सल्लागार
M/s. KICONS Limited
3

Sewage Treatment Plant

100% पुराय जाल्ले
 
प्रकल्पाची कालावधी
सुरवात जावपाची थारायल्ली तारीख April 01 2018
पुराय जावपाची प्रत्यक्ष तारीख April 30 2021
स्थिती
100%
पुराय जाल्ले
खर्च (₹)
अदमास खर्च ₹ 19,972,974.00
दिले ₹ 23,053,800.00

प्रकल्प हायलायट्स

0.4 MLD STP & RO Plant

 
Contractors
कंत्राटदार
M/s. Brisanzia Technologies Pvt. Ltd.
Consultants
सल्लागार
M/s. KICONS Limited
4

Supply, Installation, Testing & Commissioning of Central Sterile Supply Department (CSSD) equipments

100% पुराय जाल्ले
 
प्रकल्पाची कालावधी
सुरवात जावपाची थारायल्ली तारीख November 12 2018
पुराय जावपाची प्रत्यक्ष तारीख May 11 2019
स्थिती
100%
पुराय जाल्ले
खर्च (₹)
अदमास खर्च ₹ 33,054,427.00
दिले ₹ 26,606,001.00

प्रकल्प हायलायट्स

The Project consist of supply and installation of variour Central sterile service equipments and furniture etc

 
Contractors
कंत्राटदार
M/s. Steris India Pvt.Ltd
Consultants
सल्लागार
M/s. KICONS Limited
5

SITC of medical gas supply system (MGSS)

100% पुराय जाल्ले
 
प्रकल्पाची कालावधी
सुरवात जावपाची थारायल्ली तारीख January 03 2019
पुराय जावपाची प्रत्यक्ष तारीख October 24 2021
स्थिती
100%
पुराय जाल्ले
खर्च (₹)
अदमास खर्च ₹ 47,193,574.50
दिले ₹ 62,030,298.77

प्रकल्प हायलायट्स

The project consist of supply and erection of new medical gas line distribution system such as Oxygen Manifold system, Air compressors, Vaccumm Plant etc

 
Contractors
कंत्राटदार
M/s. Prenit World LLP
Consultants
सल्लागार
M/s. KICONS Limited
6

Rear Side parking and Biomedical Waste Building

100% पुराय जाल्ले
 
प्रकल्पाची कालावधी
सुरवात जावपाची थारायल्ली तारीख April 15 2022
पुराय जावपाची प्रत्यक्ष तारीख December 14 2022
स्थिती
100%
पुराय जाल्ले
खर्च (₹)
अदमास खर्च ₹ 32,678,364.00
दिले ₹ 36,058,328.56

प्रकल्प हायलायट्स

Development of parking space

 
Contractors
कंत्राटदार
M/s. Indage Development Construction Pvt. Ltd.
Consultants
सल्लागार
M/s. KICONS Limited
7

Supply & Installation of Lead Doors & Lead Glass

100% पुराय जाल्ले
 
प्रकल्पाची कालावधी
सुरवात जावपाची थारायल्ली तारीख February 14 2020
पुराय जावपाची प्रत्यक्ष तारीख September 07 2020
स्थिती
100%
पुराय जाल्ले
खर्च (₹)
अदमास खर्च ₹ 1,859,392.72
दिले ₹ 1,997,827.88

प्रकल्प हायलायट्स

Supply and installation of lead doors

 
Contractors
कंत्राटदार
M/s. Manup Infrastructures
Consultants
सल्लागार
M/s. KICONS Limited
8

Supply, Installation, Testing and Commissioning of Token System

100% पुराय जाल्ले
 
प्रकल्पाची कालावधी
सुरवात जावपाची थारायल्ली तारीख September 02 2019
पुराय जावपाची प्रत्यक्ष तारीख December 15 2020
स्थिती
100%
पुराय जाल्ले
खर्च (₹)
अदमास खर्च ₹ 2,350,459.00
दिले ₹ 2,256,449.00
 
Contractors
कंत्राटदार
M/s. Geeta Automation Technologies
Consultants
सल्लागार
M/s. KICONS Limited
9

Supply, installation, testing and commissioning of 2 nos. of 30 KVA UPS

100% पुराय जाल्ले
 
प्रकल्पाची कालावधी
सुरवात जावपाची थारायल्ली तारीख May 28 2020
पुराय जावपाची प्रत्यक्ष तारीख August 14 2020
स्थिती
100%
पुराय जाल्ले
खर्च (₹)
अदमास खर्च ₹ 850,000.00
दिले ₹ 698,000.00
 
Contractors
कंत्राटदार
M/s. Techser Power Solutions Pvt Ltd
Consultants
सल्लागार
M/s. KICONS Limited
10

Steel Operation Theatre

100% पुराय जाल्ले
 
प्रकल्पाची कालावधी
सुरवात जावपाची थारायल्ली तारीख August 19 2018
पुराय जावपाची प्रत्यक्ष तारीख February 22 2021
स्थिती
100%
पुराय जाल्ले
खर्च (₹)
अदमास खर्च ₹ 73,754,252.00
दिले ₹ 72,280,905.00
 
Contractors
कंत्राटदार
M/s. Mediconz International
Consultants
सल्लागार
M/s. KICONS Limited
11

Construction of 500 Bedded District Hospital At Margao, Goa – LV System

100% पुराय जाल्ले
 
प्रकल्पाची कालावधी
सुरवात जावपाची थारायल्ली तारीख November 09 2017
पुराय जावपाची प्रत्यक्ष तारीख March 31 2024
स्थिती
100%
पुराय जाल्ले
खर्च (₹)
अदमास खर्च ₹ 41,902,954.49
दिले ₹ 39,462,508.00

प्रकल्प हायलायट्स

The work consists of Nurse Call system, telephone system, UPS, Building Management System, LAN, CCTV, etc.

 
Contractors
कंत्राटदार
M/s. Nupur Technologies Pvt. Ltd
Consultants
सल्लागार
M/s. KICONS Limited
Similar Projects

अशेच तरेचे प्रकल्प पळोवचे

Similar Project

Motruary Equipments Works

तपशील पळोवचे
Similar Project

Full Renovation & Part Construction of the Old Heritage Building of Asilo Hospital for State Health Training Institute at Mapusa.(State Institute of Health and Family Welfare and College of Physiotherapy at restored Old Asilo Hospital, Mapusa).

तपशील पळोवचे
Similar Project

Renovation/ Maintenance of Hospitals, CHCs, PHC’S, RMD’s under Directorate of Health Services in South Goa – S.H- Renovation/ Maintenance work of Primary Health Centre at Shiroda:Maintenance Contract of the Otis Make Passenger Elevator installed at PHC, Shiroda for the period of three years

तपशील पळोवचे
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
अस्विकरण: राजभाशा संचालनालय, गोंय सरकारा वरवीं अणकारीत. टीप: खंयचेय स्थितींत कायदेशीर अर्थावणी खातीर इंग्लीश आवृत्तीक प्राधान्य दितले.