Project Duration
Stipulated Date of Commencement September 18 2013
Stipulated Date of Completion /
Likely Date of Completion
November 17 2013
Status
100%
Completed
Cost (₹)
Awarded for ₹ 5,500,000.00

Project highlights

SITC of UPS systems at GMC

 
Gallery Image
Contractors
M/s. Accutech Power Solutions Pvt. Ltd.
Gallery Image
Consultants
M/s. Frishmann Prabhu (I) Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Construction of Community Health Centre at Canacona

View Project
Similar Project

Repairs / Upgradation & Maintenance of Old Primary Health Centre at Sanquelim, Goa – Civil, Plumbing & Electrical works

View Project
Similar Project

Maintenance work of Goa Medical College & Hospital and Goa Dental College at Bambolim, Goa. S.H.: Supply, Installation, Testing & Commissioning of 30KVA online UPS systems for ICU 123 and Modular OT 5 at Goa Medical College.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.