Project Duration
Stipulated Date of Commencement September 18 2013
Stipulated Date of Completion /
Likely Date of Completion
November 17 2013
Status
100%
Completed
Cost (₹)
Awarded for ₹ 5,500,000.00

Project highlights

SITC of UPS systems at GMC

 
Gallery Image
Contractors
M/s. Accutech Power Solutions Pvt. Ltd.
Gallery Image
Consultants
M/s. Frishmann Prabhu (I) Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Renovation/ Maintenance of Hospitals, CHCs, PHC’S, RMD’s under Directorate of Health Services in South Goa – S.H- Renovation/ Maintenance work of Primary Health Centre at Shiroda:Maintenance Contract of the Otis Make Passenger Elevator installed at PHC, Shiroda for the period of three years

View Project
Similar Project

Renovation/Maintenance of Hospitals, CHCs, PHCs, RMDs under Directorate of Health Services in North Goa S.H.: Comprehensive Maintenance Contract for 2 No’s of Carrier make chillers (155TR each) for 3 Years at North Goa District Hospital, Mapusa.

View Project
Similar Project

Upgradation of Ward Nos. 120, 123, 124, staff rest rooms and other miscellaneous works at Goa Medical College and Hospital at Bambolim, Goa : SH – Procurement of additional works/items and medical equipments required for Ward No.125 and Cardiovascular Surgical Operation Theatre – Supply, Installation and Testing and Commissioning of Xenon Headlight

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.