Project Duration
Stipulated Date of Commencement
January 28 2013
Stipulated Date of Completion /
Likely Date of Completion January 27 2014
Likely Date of Completion January 27 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 3,00,41,753.00
Awarded for
₹ 3,90,22,573.00
Contractors
M/s. Daftary Descon Engineering Pvt. Ltd.
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd
Sub Works
This project involved 2 sub works. The details of the same available below
1
Electrical Works.
100% completed
Project Duration
Stipulated Date of Commencement
May 26 2013
Stipulated Date of Completion /
Likely Date of Completion November 25 2013
Likely Date of Completion November 25 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 23,50,771.00
Awarded for
₹ 23,88,737.00
Contractors
M/s. Mohan Electricals
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd
2
HVAC Works.
100% completed
Project Duration
Stipulated Date of Commencement
September 26 2013
Stipulated Date of Completion /
Likely Date of Completion January 25 2014
Likely Date of Completion January 25 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 6,324,109.94
Awarded for
₹ 5,899,999.00
Contractors
M/s. Aprant Motors Pvt. Ltd.
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd
See Similar Projects
Civil,Plumbing,Electrical,Fire fighting, Lift and HVAC works.
View Project
Supply, installation, testing and commissioning of 20 passenger cum bed lift for plastic surgery ward at GMC & Hospital, Bambolim, Goa.
View Project
Renovation/Maintenance of Hospitals, CHC’s, PHC’s, RMD’s under Directorate of Health Services in North Goa SH: Maintenance/ Renovation Work of Sub District Hospital at Ponda, Goa – SITC of Split AC Units
View Project





