Project Duration
Stipulated Date of Commencement
June 30 2017
Stipulated Date of Completion /
Likely Date of Completion August 29 2017
Likely Date of Completion August 29 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 18,41,855.00
Awarded for
₹ 1,488,459.00
Project highlights
The project consists of Supply, Installation and Testing and Commissioning of Surgical Instruments for Cardiac Department, GMC
Contractors
M/s. Overseas Associates
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd