Project Duration
Stipulated Date of Commencement
September 08 2017
Stipulated Date of Completion /
Likely Date of Completion November 07 2017
Likely Date of Completion November 07 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 797,062.00
Awarded for
₹ 441,000.00
Project highlights
Supply, Installation and Testing and Commissioning of Xenon Headlight provides Headlights Headband lightest with fully adjustable spot Module to help in operations.
Contractors
M/s. B L Lifesciences Pvt. Ltd.
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd