Project Duration
Stipulated Date of Commencement
May 12 2018
Stipulated Date of Completion /
Likely Date of Completion July 11 2018
Likely Date of Completion July 11 2018
Status
100%
Completed
Cost (₹)
Estimated at
₹ 7,800,000.00
Awarded for
₹ 11,872,000.00
Project highlights
The project consists of Supply, Installation and Testing and Commissioning of Anesthesia Workstation for Cardiac Department, GMC
Contractors
M/s. RESCARE MEDISYS (I) PVT.LTD.
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd
See Similar Projects
Furniture and miscellaneous work.
View Project
Supply of Syringe pumps
View Project
Channel Drainage Works
View Project





