Project Duration
Stipulated Date of Commencement
April 28 2016
Stipulated Date of Completion /
Likely Date of Completion July 27 2016
Likely Date of Completion July 27 2016
Status
100%
Completed
Cost (₹)
Estimated at
₹ Rs. 24,77,777.00
Awarded for
₹ 2,477,777.00
Project highlights
Air conditioned outlet for selling Horticulture produce
Contractors
M/s. Harshada Trading Company
Consultants
M/s. Ankit Prabhudessai