Project Duration
Stipulated Date of Commencement December 12 2011
Stipulated Date of Completion /
Likely Date of Completion
April 11 2012
Status
100%
Completed
Cost (₹)
Estimated at ₹ 5,528,636.00
Awarded for ₹ 5,976,204.30
 
Gallery Image
Contractors
M/s. Ask Developers
Gallery Image
Consultants
M/s. Datta Kare Associates
 

Sub Works

This project involved 1 sub works. The details of the same available below

1

Supply, Installation, Testing & Commissioning of Mortuary Cabinet.

100% completed
 
Project Duration
Stipulated Date of Commencement December 01 2011
Stipulated Date of Completion /
Likely Date of Completion
March 31 2012
Status
100%
Completed
Cost (₹)
Estimated at ₹ 2,058,320.00
Awarded for ₹ 2,406,250.00
 
Contractors
Contractors
M/s. Megastar Engineering
Consultants
Consultants
M/s. Datta Kare Associates
Similar Projects

See Similar Projects

Similar Project

Supplying and laying of 33 KV underground cable from Sub Station to District Hospital at Mapusa

View Project
Similar Project

Interior Works

View Project
Similar Project

Maintenance works at Goa Medical College and Hospital S.H.: Maintenance Contract for the Schindler make elevators installed at Medicine Ward Block for a period of one year (2020-2021).

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.