Project Duration
Stipulated Date of Commencement
November 07 2021
Stipulated Date of Completion /
Likely Date of Completion July 30 2024
Likely Date of Completion July 30 2024
Status
95%
Completed
Cost (₹)
Estimated at
₹ 19,613,927.27
Awarded for
₹ 18,418,999.24
Project highlights
Roofing work is in progress and plaster work is in progress at ground floor in the toilet area plaster work on the second floor is in progress and roofing work is in progress. Flooring works and the badminton court is in progress.
Contractors
M/s. Sun Infrastructures
Consultants
M/s. Creative Abode
See Similar Projects
Construction of Multipurpose Hall with Indoor Games Stadium of VP Nagoa.
View Project
Construction of Wholesale Fish Market at Margao – Phase II
View Project
Construction of Modern Fire Station at Bicholim, Goa – Balance works (2nd Call)
View Project





