Project Duration
Stipulated Date of Commencement January 25 2011
Stipulated Date of Completion /
Likely Date of Completion
March 24 2011
Status
100%
Completed
Cost (₹)
Estimated at ₹ 2,111,563.46
Awarded for ₹ 2,339,294.15

Project highlights

The work includes construction of soak pit, overhead water tank , connection of GI pipe from overhead tank to soak pit, laying of GI pipeline, providing and laying 80 mm thick factory made cement concrete interlocking paver blocks, etc

 
Gallery Image
Contractors
M/s. My Associates
Gallery Image
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Supply, installation, testing and commissioning of Central Air Conditioning System for GMC Complex at Bambolim, Goa.

View Project
Similar Project

Maintenance/Renovation work of Community Health Centre – Sankhali Repair/Maintenance of HVAC system.

View Project
Similar Project

Supply, Installation, Testing & Commissioning of Central Sterile Supply Department (CSSD) equipments

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.