Project Duration
Stipulated Date of Commencement September 29 2014
Stipulated Date of Completion /
Likely Date of Completion
November 28 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 23,472,531.00
Awarded for ₹ 29,708,266.00

Project highlights

Repairs to old dilapated building adjacent to Se Cathedral Church for accomodating the pilgrims attending the Exposition of relics of St. Francis Xavier

 
Gallery Image
Contractors
M/s.H Candolkar & Sons
Gallery Image
Consultants
M/s.Creative Abode
 
Similar Projects

See Similar Projects

Similar Project

Arranging Scaffolding

View Project
Similar Project

Construction of Joggers Park at Chicalim.

View Project
Similar Project

Setting up of software technology park at Udyog Bhavan, Panaji, Goa- Dismantling civil and plumbing works

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.