Project Duration
Stipulated Date of Commencement
February 19 2010
Stipulated Date of Completion /
Likely Date of Completion August 18 2010
Likely Date of Completion August 18 2010
Status
100%
Completed
Cost (₹)
Estimated at
₹ 3,316,000.00
Awarded for
₹ 3,432,000.00
Project highlights
Lift work.
Contractors
M/s. Thyssenkrupp Elevators (I) Pvt. Ltd.
Consultants
M/s Effective Architectural Services
See Similar Projects
Medical Gas & Steel OT work.
View Project
UPS works.
View Project
Upgradation of Hospital facilities at Goa Medical College, Bambolim, Hospicio Hospital at Margao and RMD at Thane & Keri. SH- Upgradation of Ward Nos. 120, 123, 124, staff rest rooms and other miscellaneous works at Goa Medical College and Hospital at Bambolim, Goa-Extension of Ward 125 for Cardiology Department at Goa Medical College, Bambolim-Goa – Supply, Installation in specified location, Testing and Commissioning of Anesthesia Workstation.