Project Duration
Stipulated Date of Commencement February 19 2010
Stipulated Date of Completion /
Likely Date of Completion
August 18 2010
Status
100%
Completed
Cost (₹)
Estimated at ₹ 3,316,000.00
Awarded for ₹ 3,432,000.00

Project highlights

Lift work.

 
Gallery Image
Contractors
M/s. Thyssenkrupp Elevators (I) Pvt. Ltd.
Gallery Image
Consultants
M/s Effective Architectural Services
 