Project Duration
Stipulated Date of Commencement September 25 2021
Stipulated Date of Completion /
Likely Date of Completion
October 02 2021
Status
100%
Completed
Cost (₹)
Estimated at ₹ 561,600.00
Awarded for ₹ 561,600.00

Project highlights

Supply and Installation of Oxygen Jumbo cylinders for gas manifold

 
Gallery Image
Contractors
M/s. Scoop Industries Pvt. Ltd.
Gallery Image
Consultants
M/s. Structwel Designers & Consultants Pvt. Ltd.
 