Project Duration
Stipulated Date of Commencement January 22 2003
Stipulated Date of Completion /
Likely Date of Completion
July 21 2003
Status
100%
Completed
Cost (₹)
Estimated at ₹ 24,631,835.00
Awarded for ₹ 29,280,000.00

Project highlights

• Length : 40 m.
• The bridge consists of cast-in-situ continuous R.C.C. T beam superstructure.
• Carriage way 7.5 m wide with kerbs, railings and footpaths on both the sides.
• Approaches on Uguem and Kalay side.
• Electric poles with fixtures on the bridge and approaches.

 
Gallery Image
Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd.
Gallery Image
Consultants
M/s. Madhav Kamat & Associates
 
Similar Projects

See Similar Projects

Similar Project

Improvement and Upgradation of existing road from Miramar Circle to Dona Paula Jetty – Balance work from Miramar Circle to NIO Circle – Phase I.

View Project
Similar Project

Hot mixing of road from O’ Coqueiro to Calangute beach via St Anthony Chapel and from St. Anthony Chapel to Fort Aguada in Bardez Taluka.

View Project
Similar Project

Design and construction of bridge at Satrem – Construction of approach roads.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.