Project Duration
Stipulated Date of Commencement
March 08 2019
Stipulated Date of Completion /
Likely Date of Completion August 07 2019
Likely Date of Completion August 07 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 21,604,390.00
Awarded for
₹ 21,378,699.00
Project highlights
Up- gradation of the existing Laboratory facilities
Contractors
M/s. Bioxia
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd.