Project Duration
Stipulated Date of Commencement
February 23 2007
Stipulated Date of Completion /
Likely Date of Completion September 14 2007
Likely Date of Completion September 14 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 5,158,850.00
Awarded for
₹ 4,838,400.00
Project highlights
Soft landscaping work comprises of soil development with lawns, foliage & flowering trees, palms, shrubs, ground covers, etc.
Contractors
M/s. Hariyalee Nursery
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd
See Similar Projects
Shadowless lights.
View Project
Construction of Girls Hostel at Goa Medical College & Hospital at Bambolim, Goa – Interior and Furniture Works
View Project
Renovation/ Maintenance of Hospitals, CHCs, PHCs, RMDs, under Directorate of Health Services in North, Goa – SH : Repair of two nos. of 60 KVA UPS installed at Sub District Hospital, Po+C523nda, Goa.
View Project





