Project Duration
Stipulated Date of Commencement December 23 2005
Stipulated Date of Completion /
Likely Date of Completion
February 10 2006
Status
100%
Completed
Cost (₹)
Estimated at ₹ 3,792,027.00
Awarded for ₹ 3,657,495.60

Project highlights

Includes hard landscape elements such as paved areas, planter boxes, fences, walkways, pathways, tanks, etc. and soft landscaping elements such as providing and fixing / planting lawns, shrubs, plants, trees and other landscape finishes.

 
Gallery Image
Contractors
M/s. Hariyalee Nursery
Gallery Image
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd
 
Similar Projects

See Similar Projects

Similar Project

Construction of Primary Health Centre at Navelim, Margao, Goa.

View Project
Similar Project

Renovations of old IPHB Building to accommodate Goa Commission for Backward Classes, Nursing Hostel and College and Directorate of Food & Drugs.

View Project
Similar Project

Construction of IInd phase of Goa Dental College & Hospital at Bambolim, Goa-Civil,Plumbing, internal electrical and fire fighting works-Balance work.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.