Project Duration
Stipulated Date of Commencement
December 23 2005
Stipulated Date of Completion /
Likely Date of Completion February 10 2006
Likely Date of Completion February 10 2006
Status
100%
Completed
Cost (₹)
Estimated at
₹ 3,792,027.00
Awarded for
₹ 3,657,495.60
Project highlights
Includes hard landscape elements such as paved areas, planter boxes, fences, walkways, pathways, tanks, etc. and soft landscaping elements such as providing and fixing / planting lawns, shrubs, plants, trees and other landscape finishes.
Contractors
M/s. Hariyalee Nursery
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd
See Similar Projects
Construction of Primary Health Centre at Navelim, Margao, Goa.
View Project
Renovations of old IPHB Building to accommodate Goa Commission for Backward Classes, Nursing Hostel and College and Directorate of Food & Drugs.
View Project
Construction of IInd phase of Goa Dental College & Hospital at Bambolim, Goa-Civil,Plumbing, internal electrical and fire fighting works-Balance work.
View Project