Project Duration
Stipulated Date of Commencement
January 01 2021
Stipulated Date of Completion /
Likely Date of Completion March 31 2021
Likely Date of Completion March 31 2021
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,082,830.00
Awarded for
₹ 1,309,825.00
Project highlights
Sewage treatment plant
Contractors
M/s. Samco Water Technologies
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd.