Project Duration
Stipulated Date of Commencement
April 13 2016
Stipulated Date of Completion /
Likely Date of Completion February 05 2016
Likely Date of Completion February 05 2016
Status
100%
Completed
Cost (₹)
Estimated at
₹ 3,125,160.00
Awarded for
₹ 3,377,777.00
Project highlights
Civil, plumbing and dismantling work for office of STPI, Goa.
Contractors
M/s. Harshada Trading co.
Consultants
M/s. Pankaj Joshi Consultants
See Similar Projects
Ancillary Works at Kala Academy Building Campal Panaji – Goa
View Project
Upgradation of Infrastructure in the rural areas under Deendayal Panchayat Raj Infrastructure Development (Golden Jubilee) Scheme , 2013 -Construction of Panchayat Ghar along with Community Hall at V.P. Uguem in Sanguem Taluka.
View Project
Supply,Installation,Testing and Commissioning of streetlight poles and fixtures along with allied electrical works for the stretch from NIO Circle to Miramar circle, NIO circle to Rajbhavan, NIO circle to Dona Paula Jetty & NIO circle to Odxel Junction
View Project