Project Duration
Stipulated Date of Commencement October 16 2015
Stipulated Date of Completion /
Likely Date of Completion
April 15 2017
Status
100%
Completed
Cost (₹)
Estimated at ₹ 2,848,685.00
Awarded for ₹ 3,502,017.00

Project highlights

Repair & restoration of the spring including walls, tunnels & disilting work.

 
Gallery Image
Contractors
M/s. Kamalakant Amonkar
Gallery Image
Consultants
M/s. Ketak Nachnolkar
 
Similar Projects

See Similar Projects

Similar Project

IP Surveillance System.

View Project
Similar Project

Interiors (Part I)

View Project
Similar Project

Supply, Installation, Testing and Commissioning of Digital Photocopier with Printer for District Library at Navelim, Margao.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.