Project Duration
Stipulated Date of Commencement
October 04 2007
Stipulated Date of Completion /
Likely Date of Completion October 31 2007
Likely Date of Completion October 31 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 23,930,239.00
Awarded for
₹ 28,515,999.00
Contractors
M/s. Goa Friends Engineering & Electricals Pvt. Ltd.
Consultants
M/s. Effective Architectural Services